2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 36
Admin space is getting an RTU. We've got new panel boards for electrical. We've got 800 amp switch gear. So, we've been talking to Bart and Co. We've got some back and forth and we're through this planning, we'll determine if it makes sense to do an early an early equipment package and get that stuff coming to to hold those dates for for construction. But from a bidding standpoint, no, I don't see I don't see an issue with the things that we do with our precon department and getting those safer dates out. I think we'll have good participation and I think we'll be able to turn our contracts pretty quick. Um, high school also has two versions because we we made an original version one uh logistics and phasing and we have a version two. So, originally at RFP uh response when we turned in our our response to the RFP, we were running under the impression that we would have no phasing.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 37
It would be a single project. We would do all of this at once throughout the pre-own meetings and Bon Co's meetings with um Amber and the school and Dr. you guys. It it it would benefit to keep the existing CTE space operational and functional while we build the West CT expansion. And once that's done and everybody's moved into the West CT expansion right there off the existing building, we could then take over and do the North Gym expansion. So, we've got two versions. One showing single single doing it all at once. And then we've got versions that show, you know, phase one and phase two. Again, we're running the costs with that. If it's split into phasing, it adds about six months to the duration of the project, which comes along with the cost for general conditions, general requirements, mobilizations. There's some other things like splitting up in phasing has now presented us with the challenge of bitting this job as well in April.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 38
Um staggered from the elementary which will go first but maybe light it by two weeks or so. Those subs or or those bid packages that bid would have to hold face material quotes and all of that until for about a year. And so that's pretty unprecedented. We get some kickback when we ask them to hold stuff for 90 days. So that'll be a challenge we'll need to work through. And there's no telling what the markup could be on holding material for, you know, through suppliers for for a year. Um there's mobilization impact. There's there's uh like I said, general conditions, general requirements. So, by doing it all in one, it's quicker and less expensive, but you lose your current CTE space that you have to the north where the gym's going to go. If you split it up, it's a little more costly. It's going to take a little longer, and um but you can maintain that programming while you do the FCP.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 39
So, with that, I'll let Seth kind of walk through the logistics, the high level logistics and and schedule, and we'll open it up for questions. Well, Neil Neil's preamble pretty much covered most of this. >> Dr. the first one. >> This is original. >> That's perfect. So, original, this would be um both buildings. CTV on the west, gymnasium on the north at the same time. And um with this um we'll I'll just I'll touch on a couple of things. um fencing perimeter um the construction area um site access and um lay down and then some of the challenges with with all this. So um fencing I'll stand up here so I can just point to it. So fencing go around the entirety of this space um uh this would all be construction area. Um three gates or three access points and then all all traffic and and access back into from a staffing standpoint um busing standpoint would all come off of state road 124.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 40
This is again proposal uh this is why you know like this first first blush it um this was our best case that we understand this this is very for the school over a duration of 20 month period. So again this would be holding 20 months um starting starting next year. So, uh, again, access this would maintain the existing student, um, parent pickup, drop off, um, but again, all of it coming off the state road to 144. Um, buses only. This was a this is a suggestion and this is an idea. Um, expanding some drive coming with buses just from here. Um, but then again, looping around in the on the north parking lot by the tennis courts and coming back out to the south. all the construction access would be um into these uh two gates and really this third gate would just be um kind of more of an emergent um scenario.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 41
Uh so lay down in red um contractor parking in light blue here. Uh what you see in dark blue would be approximately a 40 foot perimeter around the building. Um so that kind of a a phrase that we utilize at Yam is a um an organized site is a safe site is a clean site. So so all of that those hands in hand it's also an efficient site. So that's that's the the blue temporary stone construction area um for traffic and um for staging as as as work. Another thing that you'll notice is to the north. Um so there's a proposed um storm water detention area here in this in this dotted area in green and just around that will be some expanded lay down. Um mostly that would be utilized main. Um so again all construction um traffic would be separated from from from staff and students.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 42
um it's disrupt it's disruptful um to the site and to students and staff. So um any questions on that um on that first I guess both projects all at once? >> You quickly mentioned storm up there but it's because of the lot being increased then >> what what dictates that? Yeah, maybe Brian you can speak to that. >> Underwater storm detention on that north side of the road. What where what are we gathering? Is it from that added impervious that goes to CT and that expanded parking? >> Yeah. Any conversion of a like a lawn area to either a roof or or two more pavement uh will trigger expanding your storm water capacity. We the last time I I got an update from the engineers, we we are not totally sure yet what requirements they're going to have because I think they have new the requirements are new since the last time the site was improved.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 43
Um so they are still working with the county on what the drainage requirements will be. We need to finalize that. But that's a an estimate for for the time being, >> but it occurs anytime you increase the what they call impervious surface area. >> Well, that was my question. You know, I'm always concerned about the lack of real estate there that we have to work with in future. I I realize the retention area could be moved, but you know, that's a traffic area back and forth for practices on the football. >> Yeah, we'll we'll get more detail. There's usually options on where those can go or whether they go on the surface or or below ground. That's something we will continue to monitor how it develops, how much capacity we need based on county requirements, but we can't we can't update on that. >> And Kevin, I we hear we we heard you guys loud and clear about the practice football band, that area to the north of the we always are going to have that fire tank uh suppression tank in the pump house that we're going to have to deal with.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 44
But if that detention went away, we probably could slim up that lay down if it all went together and just stick to the southwest of that. You know, where you see the larger lay down and construction trailer area. Um, you're really probably not going to love football is not going to love this next version. If we split if we split it up, just to give you a fore warning here, >> I I guess I will note or just again reiterate that um the the access drive. Maybe I should make it a little bit more clear. The access drive would be like just construction of it. All right. So phase one. So this would be demolition of uh I'm sorry not demolition of CT the saving the demolition of CT. So maintaining CT program in the current facility um until the new CT is built and uh so be phase one.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 45
Um so it would be um winding management of trailers and set up down in the south area. Um very similar logistics um kind of with this lay down just expanding a little bit. Um however this would potentially give opportunity for busy brow and hair pick up drop off to be able to maintain off of road 50 and and also on so gives some more opportunities for flexibility with traffic control um widening and subcontractor traffic control would really mostly be limited just at this phase one to gate one down southway down um with with maybe an opportunity to get in on gate for construction traffic. So if split up phase one which would be May June 26 to February March 27th you would maintain that drive. It wouldn't be an impact but there'd be some impact but it would maintain and be open um for at least that first duration or that first phase of project.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 46
Um and and then as we would move as we would turn that over and move into phase two pre-engineered metal building the gym edition which would be phase two you'll see it on the next slide the impact to the north questions. Yeah. So phase two is essentially the relocation of that that area to the entire north space all the main practice area. Um it's a pretty impactful in that um our our goal would be to maintain um some level accessibility to um the a far right west bay um for deliveries and access. Our idea was that um that would be outside the construction perimeters. Um but we still maintain approximately like I said earlier about 40 foot perimeter around the building for the new gymnasium. And so that leaves just a real tight space for emergency address north of the CT when it's in operation as as this is all as the new built and then at this point um approximately February March of 27 would be when uh all the the traffic would be disrupted at that point.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 47
Um traffic to this fourth drive off and then at that point such area questions comments on that. So as a as a whole um is there a question? Sorry. >> Yeah. So, as a whole um both both u demolition both buildings at one time 40 months um separated out into the phase one and two is described. I know there's a lot of hurdles to jump. Is it possible to move construction of the west building up a couple months to where it was open by school year and you'd still kind of be all phase one? >> Yeah. So there there's there's some challenges that we run. We we understand from facilities that there's the the switch gear, the boiler, the chiller, all needs to be procured and also placed before um the new building comes in into play or opens up. So, uh some of that equipment, we're estimating the switch gear for the electricals approximately 60 month time or 60 week time over a year.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 48
Um so, it would at minimum we would procurement package. Um there's a couple so so the the early procure getting the mechanical and electrical systems ordered, delivered and installed is more challenged. The second one is we've got to let Horton Co. get through their design phase. And so that would really pull them up in a design to be able to get that released to us earlier, bid it earlier. And I just with the time it takes to to develop construction documents and get it all up to bid. It's I'm not saying it can't be done. It's just it takes a lot of u routing and permitting and getting drawings done and getting state approvals and it's challeng. That's a great Yeah, definitely. If we had the schedule time to finish the drawing to get the routing complete, yeah, that's a great that's a great option.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 49
But I just I don't I don't think we're at that there. One of the concerns I have about doing it in two phases is that we're going to absorb almost with certainty some of that escalation cost because they're holding those, as you mentioned, for holding those contracts if I were to receive that electrical. Well, even then it'd be an unknown because you wouldn't be bidding one both phases split or not split. So there's no comparison, right? >> Correct. And like Seth mentioned, it's 20 months if done in a single phase. It's one more like 26. There's general conditions, there's general requirements, there's esation clause. There's there's a lot that go there's there's remobilization and shifting around logistics and setups for lay down. There's there's quite a there's quite a hefty cost that comes along with splitting it but it allows the program you know it's against what is it you know we got to weigh it and it allows that program to stay open.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 50
I don't know if there will be there's going to be further conversations, but is there potential for temporary trailer classroom setups? And I know that doesn't do much from a lab standpoint, but could that be done somewhere? I mean, is Harland a option for the students that are in the current one now. I don't know if there's capacity or if that works with you guys programming and your curriculum, but uh there's definitely there's definitely along with the along with the cost and the schedule impact, there's definitely those kind of discussions that need to be had. So I didn't know also whether that shifts the masonary piece more into cold weather. [Music] There there there's there's um it's not ideal from a schedule to finish or complete you know CTE and be done in you know February March that's not a great time in the school year program to be switching and coming on board with that and then demoing the we know that poses an issue but you know from a construction and a duration standpoint it takes what it takes and like we feel comfortable that we can get done with the CTE by that time frame.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 51
It just doesn't work perfect into a school's semester curriculum. So, there's there's plenty of challenges that we're talking through. Um, and Kevin, you're spot on with winter conditions, like at what time of year are we going to be digging footings and foundations? At what time are we going to be putting those bearing masonry up? Is that a cost that comes along with tenting and and heating and all those winter condition type items? Well, we appreciate you guys giving us a first look at at some thoughts here uh for the board and community. We we understand with any type of construction, there's always going to be disruptions and we appreciate what you guys have done working with us on the Northfield projects. Um guys are very professional and make sure that you know school comes first when it comes to everything. So, we've always appreciated that.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 52
But we do know that there'll be challenges because this is a different different project than what we were doing on the north side when it comes to what needs to be done with some of those buildings on the south end. So, any final questions for these gentlemen comments? >> Appreciate it.
⚗ AI-reconstructed · cite from original above
2025-09-15 Wabash County, IN YouTube / MSD Wabash transcript source: youtube September 9, 2025 // MSD of Wabash County Work Session · passage 53
Thanks for letting us if there are any questions. I mean, shoot them over. We'll be happy to sit again and walk through for you guys kind of huddle up and come up with I guess there's there's a couple action items we as we get more into as we get more into the design phase with D and and moving towards getting closer to the benchmark. Um, we really do need our number um for budgeting. So, really determining the phasing is a big one and I know that's going to come along with what across board. So, we're working on >> All right. Thank you. We'll end the work session and give us a for those watching will give us a few minutes to get set up for a board meeting.
⚗ AI-reconstructed · cite from original above
2025-09-16 DuPage County, IL YouTube / wcchsd94tv transcript source: youtube August Student of the Month - Matthew Krysinski · passage 1
[Music] Primarily I do drama. I've participated in so many shows that I couldn't tell you. Probably over 30 roles. I am an active member of the band of our chamber choir. I'm an NHS, MHS, foreign language honor society. I do a lot. I think the community aspect of it like of a community high school is pretty great. It makes high school just a lot more enjoyable and easier in a lot of ways. We go is a people. Even people that I'm not really close with, it's just so friendly here. Yeah, I'd say the community aspect of it is very important to me. Don't be afraid to meet new people. There are so many people here that you wouldn't know unless you take that step and talk to them. Approach someone at lunch. talk to someone in your class because there is a very good chance that you will get to know them and you're gonna really like that person.
⚗ AI-reconstructed · cite from original above
2025-09-16 Kane County, IL YouTube / 301 BOE transcript source: youtube 2025-09-15 301 BOE Live Stream · passage 1
Danielle will be attending virtually um and remotely for an excused reason. Can I hear roll call, please? >> Dogen >> here. >> Gorman >> here. >> Hurst >> here. >> Murpha. >> Papis >> here. Ward, >> she's coming. >> Oh, she coming on. >> Was >> here. >> Give her a second. >> Daniel, are you there? She's logged in, but her mic sign, but I don't see her yet. >> We'll see if she pops in.