001okay all right we call the meeting to order at 6:32 pmus here R Landers yeah Trader yes Espinosa Williams i al to the flag of the United States of America and to the for which it stands one nation under God indivisible with liy and justice for all okay so we are currently in the public hearing correct correct okay so if we could have the presentation of the sale of working cash bonds not to exceed 3.8 million perfect and so um this as we I still got on the board over here um as we look at at our kind of process again this is this does not actually this final decision there's actually no vote of any kind tonight um but our our process as we move through this is to have a public hearing to

002make sure that everybody understands has the opportunity to ask any questions that's why Dustin's here um about about the bond sales and what that looks like um so just as an overview so when we sell these working cash bonds we'll sell them this spring the money will hit our um coffers within you know a week or so of the bond sales so we'll actually go in our in this year's fiscal budget since this is our this is our two-year cycle that we that we do for this um it was in our budget it was something that we were anticipating doing um because the conversation was to have it so the our bond sales would actually increase our total tax rate by a nickel um we have an estimated net proceed of 3675 million um again

003that increases our bond tax rate by nickel and it our repayment obligations from FY 28 to fy3 we'll look at that more in detail in a minute so if we look at just that tax rate the portion of the tax rate that's the bond repayment kind of what that has looked like for us um fy20 it was 46 cents uh then 44 42 in FY 23 it was 41 a half that's kind of been our Target um last year because of our eav jump it it dropped down to 7 and then this last year we bumped it back up to that 41.5 cents so again that's that um Bond repayment that anticipated rate so our previous Target was at 41.5 cents and because of the previous conversations that we've had our future Target's going to

004be a nickel higher than that which is 46.5 cents that'll increase our total tax rate from 285 to 290 um that extra nickel on $100,000 worth of market value it's about $17 a year if we look at our existing repayment schedule again as it sits Now 26 27 28 so as it sits now um we would be done with all of our repayments at the end of FY 28 so in our last entrance payment would or our last payment would technically be December of 27 um and as we've done in the past uh this will add two years on to that so FY 29 fy3 so our last actual payment will be December 1st of 29 in that fy3 year so the bond proceeds going to fund facility improvements that we've had because our bond

005uh proceeds are going towards facility improvements they're actually um able to be tax fre on the investor end and therefore we get therefore the investors get a better rate which means that we when we borrow money get a better rate so we so we so we kind of want to take a minute to take some stock and say okay well what are we selling these bonds for um some of our solar um project the bond will help to finish paying that off um we just recently even in this fiscal year had some of Sol of the solar payments um our summer Our Last Summer updates and then the substantial hbac updates that we have scheduled for this summer all of those things will be paid for by this um this is a pretty cool picture

006um it's the the solar field on top Blackstone um and so again we're just trying to kind of walk through some of those things that we just talked about um our solar project um North Brook upgrades leachers and hallway and it's so funny because take a you look at this picture and you're like get Neath that's a hallway you don't see all of that old angled glass that just looked D and yucky dated and yucky thank you perfect um again North Brook um widening and updating the Teachers Lounge so DUS I'll go into a little bit more about this this is this is a picture of how would you like to work on this and keep this running right um yeah no thanks thank we have DUS um and so this is you know he'll

007talk about this part of our old boiler system and all of that is now going to be replaced with this that's amazing right and this unit actually um will provide heating coing to the room that it sits in and also it sister room on the other side of the Mason wall and so each one of those units provides Heating and Cooling to two different rooms two different th stats should that big thing was just for that so the so this so these two big things here the two boilers that's that's what would circulate the steam through the whole building um and so then it'll be replaced with these individual units so there'll be one of these per two per every other classroom for sure for sure so I think it's important to kind of get

008a visual of what we're borrowing this for um and so any comments uh from the board on that process or are there any comments from the public on the lawyer literally says I have to ask that so thank you m presid all right so we have a motion to adjourn our public hearing please I move to adjourn the public hearing Landers yes commas yes yes right can we call to order our regular meeting at 6:39 p.m. please call commas yes R Landers here C here Trader esposa Williams already did the Pledge so we have a motion to approve the regular meeting agenda Trader yes C yes Landers yes yes no visitors or public comment this evening move on to motion to approve the consent to G I move to approve the consent agenda including 5.1

009disposition of minutes 5.2 payment of bills 5.3 District Treasures report 5.4 imp activity fund report cafeteria report and 5.5 person C yes Trader yes commanders yes who yes yes information item 61 have any fo we did have a Foya we annually get um a appr Information Act request from the Illinois retired Teachers Association um so they can send out information packets um to their people that are going to join their ranks that was the only one we had 6.2 administra reports auditor presentation and maintenance so um I have a couple other things I would like to chat about and we can do that later in discussion um we can get our presentations rolling um and we haven't seen Russ yet so um as Dustin gets started um I'll go out front and see wandering around

010in the parking lot um but I will uh turn this over to Mr Ken a little presentation for all right a little introduction so my name is Dustin Ken I am the maintenance director here at Mota District 289 um I'm responsible for the care upkeep and functionality of all the district's facilities to prepare a little uh presentation just to kind of highlight some of the things that we are working on uh mechanical up time so my first day here me and Brad and he said there's one thing that needs to happen is things need to work so I started coming up with a prev maintenance plan uh number one thing preventive maintenance the more we can stop things from happening or get eyes on things the faster we can repair them this also reduces expensive

011Outsourcing uh this picture that Brad showed earlier this is actually the condensate pump at Northbrook um the Steam and condensate lines so far this winter I've had about eight major leaks we've handled seven of them in house so huge savings huge savings there uh this is a picture of a pipe going into a manifold at Lincoln uh the geothermal system at Lincoln uh the internal chemistry of the piping was extremely acidic um it was about 4 and a half when we should be at 11 so has been eating away at the internal piping and uh the fear is always that there's 24 400t deep wells in the back of that and we don't want any of them to e so we are slowly addressing that internal chemistry uh the reason we're going slowly is because

012as I've found out there it's exposing leaks as we put in Rust Inhibitors increase the pH we're removing that rust from the system and exposing a few leaks uh but if we do it slowly it's something that we can manage uh some process improvements floor maintenance huge uh there's been an extreme lack of floor stripping done and the previous decades uh so we have started that here's a good example at Blackstone this is the first grade Hall at Blackstone and this is something we stripped over the summer and this is about two decades of wax build up uh when you walk in these buildings you might not notice this uh but I do so uh as we do this you can make this VCT Floor look as if it's brand new uh a custodial task

013assignment and training uh huge there was a lot of inconsistencies in our custodial uh training and chemicals used we're going to try we're trying to get everything together uh so that it's one easy to follow thing we actually uh last year I made a standard operating procedures book for all the custodians uh I borrowed stuff from several other school districts around the whole country I would just call them and they were all very great to help us so that's been very useful uh economical projects uh completing projects in house to avoid costly Outsourcing that's probably my favorite thing that I do um it's something that as I like to say moves the needle we save money it's getting done um and we're not duct taping a band doing anything it's getting done appropriately and I

014reach out to professionals all the time local Carpenters Local electricians for information they're all they pay taxes they're all very happy to help uh some of the projects we've done is bathroom Renovations which I can got some pictures here this is from Northbrook this is a before picture um and then just for less than $1,000 this whole bathroom got painted new flooring aoxy and flooring mirrors and uh most of the money was just in toilet fixtures uh storage sheds we have two storage sheds at Blackstone and one at Lincoln those got new roofs new siding new paint new trim basically brand new sheds uh we spent less than $3,000 to do all three of them a single shed would have been that much uh lighting internal external lighting huge uh North Brook still has a

015lot of fluorescent lighting which requires a Bast basts are like 20 to $30 normally they would replace that we can convert them to LED for about $20 saving money and again they last easily twice as long uh some other projects we've done this is at blacks and also in their steam room this is a this sink it's hard to tell but this was very close to the ground um but the sink was mainly used by the teacher in that room to clean paint brushes and various other things so for a fraction gave them a nice utility sink uh here's an example of the sheds uh we also put the names on them just because uh I have some employees that like to do woodworking so why not um and again new siding new trim work

016painted stained new flooring the one at Blackstone actually we tiled around the entire thing because it was sinking um this is at the track this is the old locker room um you could almost see into this building it was so uh bad for very little money again we resided it with shiplap uh this going to get painted this spring uh one of our mo more extensive projects was this front area at Northbrook this overhang here the ceiling part of it was a starting to fall be none of the lighting worked because the wiring was so old uh so we ended up tearing this whole entire ceiling out me and another employee over it was election day we did it uh when no one was around we discovered a host of issues took care of them

017all shed the whole thing up um I even communicated with mock carpentry to make sure I was doing things correctly and uh new lighting all integrated LEDs again cost savings it's brighter and it just looks 100 times better uh this this is right from the uh Teachers Lounge which you saw and this wasn't exactly in our scope with grp to do this ceiling but the grid was brown and the ceiling tiles were all pretty decrepit and bad so for very little money we put all new ceiling tiles in and primed and painted the grid uh some future projects uh we're going to continue with the bathrooms and lighting uh the concession stand at the track is in need of TLC me and Brad are in discussions about what we're going to do with that and

018a major problem that I think almost all school districts have is storage and again me and Brad have been in discussions about how we want to remedy that we we used to store a lot of stuff at the track there's no good way of getting to that without driving over the track which is very expensive and not worth driving over for a desk at times uh but we're working on that and and who really knows what tomorrow will bring uh any questions questions but thank you so much you know we're uh we're very fortunate to have Dustin as a part of the team not only that does he have a really great skill set um but he's you know as they say a m boy and you know he graduated high school here like three

019years ago or something um and he has he has an incredible work e think he has incredible ownership of what's going on and so um he's really taken um processes that had largely gone ignored uh for for a while and really brought them up to speed brought them up to code put new put new ideas in place and so um we could not he hears us all the time I'm surprised his head fits through the door but um it's starting to get annoying right yeah for sure were super Glades part of the team couldn't be have here thanks and now also somebody who saved our bacon um it's my pleasure to have Russ here um Russ Rumble has been working with Grins and Associates for I'm GNA say a day or two a period of

020time yeah some undisclosed period of time um gens also um has done the high school auditing for a while and and um when we got unceremoniously dumped um last year uh I called Russ and I said look hey come on look we're super good to work with which he found out was actually true um and and you we can be late it's all good just can he's like he's like well I don't know so like three weeks later I'm like calling back I'm like come on please he goes as long as you it's as advertised as long as you guys have your stuff order as long as you know what you're doing and I'm like look we've got a we've got a a group that full disclosure they haven't been doing it that long in

021their current jobs they're really good right they're conscientious and they they put stuff in order and they take take care of things and I wasn't wrong was I your your team your team had pretty good good run we we cross our we cross our fingers if we pick up a new client I will say that it's like hold our breath hopefully things are in order and and the folks are in place that can and the The A Team is pleasantly surprised yeah for sure so Russ please because we do have our our share of ones that AR right so I I don't know if you've gotten the reports themselves um but I do have a so yeah what we needs more paper right everybody has a oh you have it okay you get an A

022I you so awesome um so I am going to cover a few things in the report I mean the focus is really the handout um but but I at least want to cover some information in the audit report the report itself so you know so really when when the board hires an auditing firm we're auditing the financial statements okay not necessarily producing them um we're auditing them so the result of that audit is really uh contained in pages in in this it's the auditor's report okay and it's also there's another report in here over internal control over Financial recoring compliance and other compliance matters so really these pages right here are the most important Pages as far that this is what you hire us what these pages right here um we issued an unmodified opinion

023on the financial statement that's the same opinion we've received in the past which is if we historically think about it is um it was thought of as a clean opinion if you will um so so the opinion um is a modified opinion and also the other report we didn't note um we did not note an internal control matter or a compliance matter so that's all good okay um I I do have and I think this is probably yes if you if you have the report I I highlighted mine at the bottom it's it's yeah so so I think everybody needs to know about this paragraph right here and I'm going to read it just because um the financial profile score if you look at the handout and you look at the bottom right and you

024look at the financial profile score as it's calculated in the AFR what it goes from 3.9 3.45 3.2 okay so that's been declining right and that uh currently it's in financial review and this paragraph explains some of that so I'm going to read it and I I think you I think everybody here is nor to understand it once once we read it so the district has accounted for cap a capital project in the operation and maintenance fund that is you had construction that was being spent out of U the operation and maintenance Fund in the previous fiscal year the district evaded $6.6 million of working of the working cash fund to the operation and maintenance F so not in June 30th the 24 but the previous year we move the district moved 6.6 million out

025of working cash over to the building fund um to finance the capital project expenditures during the current fiscal year the operation and maintenance fund had a deficit $ 2.12 s million that is you know if we look at the revenue and the building fund minus expenses it really did show a negative right $2 2.12 s million most of which is a result of ongoing Capital project the operation maintenance Fund in current 2227 of capital public that is you know payments towards the project right the current year operation and Main fund deficit is resulting in the requirement to have a deficit reduction plan so ISB doesn't like the fact of the timing of the expenditures now is that you might get a hold of ISB when they when they come out with the financial profile score

026and say hey wait wait wait you know I mean this is really just a matter of we moved 6.6 million in 23 and we spent in 24 obviously you spent some of it in 2023 as well but um so we did note that in here and that's kind of a you know ISP should kind of focus in on that and say oh okay maybe we need to modify um the 3.2 to something different than but um I think that's uh an item in here that's worthy of noting um let me see here yeah I mean if if you looked at this financial statements it would have the negative - 2127 million in the uh in the educ or I'm sorry operation Nam f um I don't know if you have page numbers on that but

027on page eight which sometimes they have numerous pages on those but on page eight has the fund balances of the district and you know one thing we we like to take a look at is okay the fund balance of the Ed fund building fund um transportation fund and working cash those are the three you know the core funds of the district like to have about three months worth of of um months worth of expenditures remaining in fund balance and the Ed fund had 2.5 month if you do the maap you take the ending fund balance divided by the expenditures um I don't know that the operation maintenance fund that's that's still again that transfer that Bond proceeds really does skew that fund and then Transportation fund was about three months so you know as far

028as fund balance goes it seems like that's within parameters what is a good Financial profile score 4.0 okay that's the best that's the best okay yep and the average um now when you say average you know so if we if you look at where you have been on this you know so this is really at the bottom of the page here it has the last three years right so that 3.9 um might be a common number typically that that 0.1 um off of a 4.0 is because there's debt off um so debt is part of that calculation um I would say the past couple years have been probably the deficit spending in the building fun is what's dragging things down um so yeah that being said a lot of I I I won't say across

029the board most districts but I would say quite a few districts are going to be at that 3.9 less are at the 4.0 some of them may be at 3.7 right I mean so it just Falls in that in that range as far as what we typically see and you know so this year um you know that paragraph that we read you know there's a timing issue I've never come across that um until this year and came across it here came across it in another district and we wrote it wasn't identical but it was like they received Grant funds in fiscal year 23 they spent them in 2024 and it was $2 million you know it was a weird Grant um so we did the same thing we noted it in here and it it

030definitely impacted their financial profile score would it have been less had we have only moved what we were going to spend in that fiscal year and then done a second um there would have been less yes it might have BL it might have smoothed out some to where you wouldn't have taken the hit maybe all in that year so yeah I mean IB likes having basically a break even right um but did you know how much you were going to spend did you know how did you know the timeing of the construction I don't know those answers you know sometimes it's really tough to know how much should we move versus what is the cash flow of the project so um I just have a couple more things um here out of the financial report

031itself you know buried in the notes there is and if you if you find it here there there is you know hey there's outstanding debt $4.6 million $ 4.66 million as of June 30th um and if we if we flip the you know it does have hey there's a there's a debt repayment schedule in here too you know when when if if you didn't have to borrow additional funds in 2028 the district would be completely paid back right and I know you probably just had a meeting to we just did like working C yes yes so and and another nice thing here you know I don't know if it's ever been pointed out but there's a um a legal debt limit which calculates out to about 20 million this helps or not I wish I

032had page numbers on this and I do not um but you know so there's a legal debt margin here yeah so there's your debt right and then if you CLI the page there's the repayment and here is the legal debt margin so so you know there's a calculation hey you can only borrow so much right so $20 million roughly in this District as far as a legal debt margin and there's 4.66 we said it's outstanding so there's 15 million that the district could borrow now as of December what you've already paid down some more on your debt as well so this changes but still um you know three4 of the debt limit is free right it's not encumbered if you will uh the one other item you know I I guess it's good to point

033out there was a prior period adjustment so what is a prior Peri adjustment we changed the presentation of something from the prior year presentation okay and that was that the um the sales tax you you do receive some sales tax proceeds they were resident in the operation maintenance fund building fund whatever you want to call that really needs to be over in capital projects I think we went over that on exit hey look put those sales tax dollars over in your capital projects two funds that it can be typically is going to be capital projects and over in debt service and I don't think you have alternate Revenue sour and you probably don't get enough sales tax to even consider it but but anyway so that's something to note as well okay so that's this

034uh or that's the audit report so clean opinion really didn't note anything we did have the issue of the financial profile score we made a note to ISP and I think you could follow up with that as well um once they give the designation out um and then we have prior period adjustment really moving those dollars out of building over to reporting wise over to the uh capital projects sorry building fund capital projects is it fund 21 I I kind of forget I feel like you have a sales tax fund and I'm not sure what it is off yeah we use 21 yeah so so it's and fund 20 is typically what this the building fund so I can see how that would happen Okay that being said the handout Okay so we've had a

035handout here and so the top section of the first page has the analysis of fund Equity far right hand column June 30th 2024 start at $34 million of equity and what most of that is the interior component you know the building uh the the tables the carpet whatever $26 million and also there's funds restricted for specific purposes so we get to the net equity and the operating funds $5.45 three million operating funds Ed fund building fund Transportation fund working cash fund all combined um so you know there's a change there a negative 2.9 Million again we said well you know we saw in the building fund you know there was a draw down of 2. some odd million dollars that's included in that so the the center section of this page would be the results

036actual compared to budget Ed fund building fund Transportation fund like to see plus or minus 10% and most of those funds are that way you see the building fund well had a capital project Fund in it that's probably hard to dial in as far as cash flow go and um yeah the transportation fund had 116% so you know we've already talked about the bottom part of the page here the financial profile score and there there is some additional that'll pop up again within the report but really the financial profile score is something to I key in on that bottom section um next page of the report again this is just those operating funds um so if we look here fiscal year 22 23 24 and the changes um you know so the the the district

037brought in roughly $2.5 million less than the previous year you know the positives are real estate taxes right 58,000 and the big negative is the federal Source funds right um and that's going to be primarily what your Co money right I mean it seems like Co money kept coming well you're to the point where the fun is done probably with the co Mone um and then you can also see in the far right hand column just tracking through through the expenses ative -2.8 million that was the capital project that you had going so less expenses in the current year compared to the previous year as far as U the building fund goes went from 6 million to 3159 million overall U you know if you track 2024 all the way to the bottom $2.8 million

038deficit this is before transfers you know so if you if if we happen to have a transfer of $4 million being working cash over to another operating fund that would be before that transfer so okay next page of the handout um you know where's a where's a dollar coming from well um you know 39 cents on a dollar is coming from real estate taxes other local sources 14% that could be your interest earnings that could be corporate replacement taxes that could be the Food Service program then you can see evidence-based funding 29% other state sources seven and the Federal 11 um next page of the handout you know historically what's happening within the categories and what is important to the district um well the real estate taxes are really they're the most important factor as

039far as a category of Revenue but that evidence-based funding is really important as well here isn't it you know as far as the magnitude of revenues coming in the other state the other local sources again would be driven by corporate replacement taxes it' be driven by interest and uh the other the other state sources would be your transportation Aid and U maybe some special ed funds and then the federal source of funds again you can see that it was high it came down and we saw that a couple different places and that's going to be primarily the co funds that are getting less next page is the handout um so this has uh categories of expenses for the Ed the building trans a and then the total and um and looking at things uh you

040know I I would typically focus on salaries and benefits right I mean so total salaries and benefits are up about 6% went from 9 9.2 to 9.8 um overall there was actually less expenditures in these funds than the previous year but again we we focused in on what the building fund right um and it had um the capital outlay the previous year and this year not that it didn't have any Capital outlay but it was less than the current year next page of the handout and so this is going to be unique and it would have been unique last year too if you put together P chart where's dollar spent typically you're going to be pushing 70 to 80% in salaries and benefits but what there's the $2 million project that was spent so it

041does skew the figure some in the fact that Capital outlays 14% of the pi versus you know then then I would assume that's going to shrink up I don't know if you if you have those projects continuing one more summer one more Summer Okay gota and then the next page of the handout uh what categories what are what are the categories been doing you know as far as expenses and you see salaries and benefits in increased in the past you know few years um same with purchase Services same with supplies and materials and then you can see the capital outlay project in the previous fiscal year how much was spent and then other objects is typically going to be payments to the your special education Cooperative um next page of the handout is uh Revenue

042this is a simple you know Hey where's Revenue where is expenses and we said you know so the in the current year the expenses are above the revenues um again it's before transfers but we already talked about that you know there there was a um you know two point and we can look at front page or the second page but there was a couple million dollars there that uh the the expenditures exceeded the revenue primarily due to the capital project same thing last year probably and then you can see going back to 2022 revenues were higher than um than the expenditures next page of the handout and these are just data points and probably could put more in here but you know the average daily attendance that's from ISB that's so that's a that's a

043number that is reported to them and it goes into the calculation on the bottom of the comparative estimated cost per pupil um as you can see 878 919 921 and then the bottom how much does it cost to educate the students so so again 2023 the most recently information from the state on average grade school district 1,609 and the district is spending 12,430 students next page of the handout um so so we saw on the one page the categories of Revenue what what is happening within categories of Revenue and we saw real estate as the biggest piece well this is something to keep an eye on you know the assessed value right so the assessed value is part of the equation to come up with how much revenue does the district receive for real estate

044taxes and you do want to see that increasing and you can see 272,000 272 million almost 273 million to 290 million then the tax rates on the bottom um went from 2 what 2.7 to 2.8 as far as the rate is concerned um fund balances so fund balances there was a draw down again related to the capital project that was in the building fund primarily but there was a draw down from 23 to 24 8.4 million to 5.4 million and then the next page you can see the debt um you know and again three data points there isn't that many data points here but you can see went from 3.5 to 5.6 4.6 after the payment so anyway so so that's that's the report I have um you know so number one unqualified number two

045um really not anything to note you know specifically within controls or compliance those are all good um I would say you know the one thing I mean obviously I definitely wanted to see hey the the financial profile score did drop there's a reason for it and I think ISB should be able to pick that out as well I don't know if they'll change the score but anyway so those would would be what I probably focus on the most um and then um yeah fun balances look they look okay you have some fund balances that's good right um it's always good to have again three to six months is what we look at as far as us the the state or ISB you start accumulating over two years a fund balance that's typically a no no

046so anyway that's the report I have I don't know if you have questions comments concerns see is there anything so when when we specifically for the purpose of like the cap of projects like we put air conditions our buildings or we large painting and we changed our security entrances and those kind of things that we're doing specifically for our buildings with that shortterm um borrowing is there a different way to reflect that where you're not going to see such a massive drop yes there there is a different way um I'm not saying what you've done in the past is is wrong right just by saying this but you have a capital project fun that you could run all that through fund 60 um that could be another option and what that does is it pulls

047it out of the operating funds and keeps the building fund I guess yeah I mean it would be more more of a trend right I mean it would be just yeah it would be more of a trend and it pulls it out of the financial profile probably you know since it's it's a different it's not an operating point right yeah so you could do it that way again I don't want size would I mean I we have had other districts that have done the same thing you know it's working cash fund transfer to the building fund and we've we've built buildings out of it we've seen buildings complete buildings trade school you know and it's like well if that's what you want to do there's you can do that so the thing yeah the thing

048that I really liked about uh um Russ and his team is that having a different auditing firm come in is it it wasn't the exact same process as what we had in the previous couple years and so they literally asked a fresh set of questions looked at things differently and you know a couple of times I kind of thought in my head the last per person didn't ask for that or want to know and so it was just it was just really good to have you know a different perspective and and and so for two different Auditors back to back say U yep no R red flags with your processes the things that you're doing internally um you know you're doing a nice job you know it'd be nice to have an office where we

049have you know a dozen people and everybody has their own and there's a huge segregation of responsibilities we don't have that and so um you know we do that we do that we do that well um you know um and for a couple different a for to come in and take a look at our practices and say you know that we're doing a nice job you know that that makes us feel good okay and again we'll see you next [Laughter] year thanks for saying yeah yeah yeah I mean your team did we did appreciate your team I I will say that um because like I said we we AIT we audit too many schools freely admit that and it's tough to bring another one on board and uh you know when you do you hope

050it's you know because out of the scope of what we do we definitely have a group that whether you know you transition the position or this year we had somebody that promoted the secretary to the bookkeeper and it hasn't gone well you know so there's those types of things that you know it it was a it was a pleasant experience we appreciate it thank you so no thank you thank you much thanks app sure um ahead hey you're doing a great job here or a you know in that experience you could possibly use 60 or for giving you for sure other ways yep yep they they sit down us um on exit and they got a long list of you know they we only hear this part you hear a whole lot for sure for

051sure yep yep no they're they are super thorough nice um so so we had had um a presentation from the athletic director last um last time out and um the question was asked what did what did those try out numbers look like um you know how you know what are we doing and then you know I had had um a followup conversation with the middle board member and so I want just kind of wanted to put together just a little kind of um you know um sheet of all the different activities that our kids have at Northbrook and so um again you can I'm just putting this in front of you now you can digest this at your leisure and you know if you want to have a follow conversation at a different board meeting

052you can certainly do that um but this just gives you um kind of a snapshot of all the different opportunities that we have um for our kids at Northbrook um on on the where we do have tryouts um we've tried to list the numbers of the of the students who tried out versus how many spots we have on the teams um I try to put the grade levels in there so you can kind of get a get a sense for you know as as the kids get older they do get more opportunities um I know that we've had some internal about um adding orts because that was a um we've already added cross country and Es Sports was those um was one and two with um as far as student interest goes off this interest

053survey that we did last spring um I don't I don't know that we're going to get that done this year but it's because there's it's it's a it's kind of a new Beast for us um and so you know we're taking taking our time we're going to make sure structures in place and we do it correctly um but we're you know we're continuing to look at that and and kind move into that um but again it's it's along the same you know vein that we've talked about making sure that our kids are supported making sure that our kids have opportunities making sure that um you know we don't we obviously don't offer everything that our high school does but you know just to give kids different experiences I think this would be helpful to communicate

054to the high school because I see at the Freshman level that sometimes they struggle to populate the full teams in all areas sure but it could be an unintended consequence when we have 41 kids trying out for something in seventh grade and we take 14 and then we have 35 trying out in eighth grade and we take 14 like there may be some interest from the high school level of you know how they have like the club like they'll do like the camps or clubs or it just might be interesting to talk with them about the potential opportunity that if we're having to turn 25 kids away that are interested in a sport especially if you turn them away two years in a row the likelihood that they pursue that a third time in high

055school in high school they haven't had a chance to play in junior high like it just it might get an opportunity whether they want to partner with us on like a a coopy type thing or a camp thing or something that gives them the kids because I'm just fearful that when we're only holding 14 spots which I totally understand why and then they're looking for a bunch across so many more activities and they don't have enough then y for sure yep and and we have monthly meetings with the high school and so we can definitely add that to our agenda for our next me for sure Mee I don't know what other sport play wrestling and we don't do wrestling so here's these basketball kids that could go to that that's me yeah or even

056like it's the best like a lot of times they do a camp for like cheer this year for the very first time is doing a sixth seventh and eighth grade like instead of a little girls cheer camp they're doing like a junior high cheer camp run by the high school like so we had um 33 seventh graders try out for cheer and we only took eight from here for here but maybe like if the timing of those types of activities and opportunities at the high school could still give the kids a chance to try to engaged in the sport whether it's a sport we offer or don't offer it would just be a nice opportunity to keep interest peaked in kids that maybe were not chosen in the E that get to officially do it

057like ways to continue because I I think they do that for a lot of the sports I know they do for football they do for cheerleading um B basketball had one yes they do basketball has a camp so the the high school has these camps where our younger kids to continue to have exposure and I'm just wondering if there's more opportunity like maybe they two times a year or maybe the timing of them is tied more to the hey we had 41 kids interested in this we can only take 14 here's 25 I've still had a peaked interest like maybe doing the club or whatever over here after school as opposed to parents having to go over there like it just may be an opportunity to collaborate a little more closely across Athletics it seems

058like kind of once your Co group of kids is chosen at whatever grade it kind of stays that way with couple of them moving in so those extra students that don't have a place to go can you say at least eighth graders maybe mingle with the ninth graders and obviously they can't play the sport they could do practice they start right right that's what I'm hoping is there some ways for us to continue to even the SE seventh grade like seven either the beginning of the Season or the end of the season or like a couple practices in do something to just keep the interest level up because I am we don't have a lot of club sports around here so unlike areas where yeah club sports are super popular without a long distance commute

059which is not the case here these kids don't necessarily have a lot of other opportunity to keep the interest or you know and then there's the financial burden of a club Sport and so yeah great Club basketall was canell this year because there wasn't enough so those many of those kids were the ones that were pulled not on these teams right but I think too the clubs present a different challenge because the cost yes yes timing the location but if we can keep it free or very inexpensive in collaboration with them the benefit is on both sides we keep our kids inre we notice great things for them and then they potentially have a feeder for their programs the kids get over there with Annie and grant money that going around at you children has

060any of that ever made something um so the so they have had um you know they've had some uh programs during some of our early outs um and you on our half days and so yeah so there have been some some programs that they've come up with with some of that I know next isn't it DOD this is incredible what we do offer it just makes me a little sad to see the numbers that we have to turn away it's like the amount of kids that are looking for something to do y um that made it to the tryy outs and tried that I just hate to see us you engage them in something I know we had talked at one point too about like maybe a club of Just Sports Club or something like

061that where they would come and try different things like right like just be active and have a place just to me that's a just such a huge piece of school at this age is finding that sense of belonging and for sure do schs have for junior some do and we do did I don't know we do but we did have that at like I know for sure basket other grades we did but then they said the younger grades it's more common but the older you get might have an A but by the time you get to eth grade you don't necessarily carry an AB which is so weird because then you get to high school and you have freshman playing at VAR City but you still have a freshman team or a JV team like

062there's so much opportunity like can stick them on so many places when they get there but yeah no we can definitely continue those conversations for sure be great yep of course that was it for yours okay we had no board committees or reports no but we probably will fire up the health insurance committee here soon yes be do we have any numbers yet we don't but I will gather those um you know we should have pretty good numbers um here shortly since with it being with the year being half over that R out okay Ming on to action items our IG was the school for algebra primary difference is it's here correct so the teacher is moving and not all the kiddos our teacher our teacher yes and so it will save the cost of

063not only transporting kids but the cost of so what's the is the IG for the curricular resource then yep so the IG is basic it basically says um yep yep it's going to be it's going to be um our teacher they need to be credentialed um they need to use our materials um still continue to use all the same vetting processes um that we've used in the past and so um a lot of the IGA is the same the big change is that it's going to be our teacher and the kids are going to be here the Holy Cross students we will still make it available to the Holy Cross students as well I don't know on funding Mr they would normally PID High School something to do that so that we come here I

064would I haven't had those conversations with Mr sh at a Holy Cross but we have conversations yeah usually it's the first period or the last period of the day um is it capacity to do it we have teacher capacity will be our grade instructor that'll take that yep and Mr wmer has actually taught um algebra before when he was I can't remember whether whether he was a Peru or S but he used to teach the lp high school algebra when he got along with his eth grade so he's very familiar with this for sure it be great all right we need motion to approve Trader yes pass yes Landers yes yes 72 school calendar specific it's almost identical to this year and he still very closely aligned with the high school yep um the superintendent

065of high school I sit down and and work through some things and try to align things as much as possible um and they continue to take a teacher Institute um in October that we're in session um but I we we make sure that our breaks line up as much as possible um is there first day school far off from ours no um I believe I believe in the past I believe this year their first day of school was Wednesday of that week and ours was Friday with kids and so it'll it will be at least that close if not closer um this year approve 26 Manders yes trer yes yes all right is there anything else for discussion yeah um just wanted to um put a reminder for everybody um for upcoming board meetings is

066when we we start our our annual visit cycle to schol two of schools to other buildings um and so the February meeting will be over in Lincoln I assume it will be in their AP room next to the office because they've updated that a little bit uh March will be at Northbrook which I assume will be in the Teachers Lounge and April will be at Blackstone which I also wasum being teacher just let him know there's going to be a prize at the end for that remember when we had those cute notes from the class that we were in that was so sweet super all right why do we do um one coming up next week I think so in February so it reminded me we have two months where there's two days off a

067Monday and a Friday I was just thought that was weird super weird right yeah yeah so that's um and it'll be again the same next year and so it's parent conference parent teacher conference week and so it's a even though it's a three-day week it's super busy um because two of those three nights um everybody's working you know 6:30 to 7:30 at night taking care of conferences and so then the Friday off is the when you have conferences at night then you do that for two nights and it accumulates basically a day off but it's really nice in that um My Philosophy has always been will always be whatever whatever you can do to break up January February March until spring break you you take advantage of it because it's the absolute worst stretch of

068the year the weather's cold you can't get outside it's it's kind of the dog days of the school year and everybody's just trying to get into spring break in one piece so um whatever I can do in a calendar to build in some Quicky little things or brakes or something to you know give everybody a a quick breather um I think that's super important if there's no other items for discussion can we have a motion to l