Transcript

Verbatim source text

001okay can I get a motion to come out of executive session at 5:40 Katie Katie second Diana Diana all in favor I I oppos okay 7 Zer all right we'll call to order the Monday January 27th special meeting of the board of education at 6:41 and we'll begin with the pledge please 5:41 United States of America just a few announcements please take note of the emergency exits on the side behind you there's no smoking anywhere in school property and this portion of the special meeting is being streamed on our district YouTube page so uh before we jump into the agenda itself just a couple of uh notices um one uh we have an addendum to the consent agenda that was added uh at the end of day today and also we are pulling number five

002the mo MOA from the consent agenda okay so we're adding one item and we're pulling one item okay um just want to make note also in your folders there was a memo regarding changes to the um tax exemption for volunteers um we did this I don't know a few months back and this is additional changes that the governor is allowing us to do if we choose to I'm I'm fine with what we did but if anybody's interested in discussing this we can talk about it at the next meeting we'll need to hold a town hall um or a public comment session and and then vote on it if if we want to entertain it if we don't want to entertain it then we don't need to do anything okay so just take note of that

003and and review that and we'll go from there all right moving on to Old business we're going to begin with the future of Walen elementary school thank you Mr President um so superintendent Aila asked me to follow up on a few items for you tonight um first on our old business is the future of Walden elementary school so this would be a followup to our conversation that we had at the last board meeting uh up on the presentation you'll see uh we believe this is what the consensus of the board was asking us to look into um so regarding uh mck Elementary School um we expect to have this information for the board at the March 10th meeting uh we will provide a cost to reopen uh mayber elementary school as a school uh and

004also provide information to evaluate existing spaces ver State guidelines of that building uh second regarding Community engagement uh we will provide different strategies to increase engagement and to make sure that the entire VC Community is aware of what is happening and everyone is engaged in the process uh regarding the Princeton model we will share different configurations and what the impact would be on students and the community and uh lastly cost of student reallocation uh relocation during a renovation project um so this would be the scenario if the board chooses and the voters approved to renovate Walden Elementary School um we will have some information on that any questions in here or no no I do have a question sure um or actually a clarification I didn't realize exactly what the Princeton model was when we

005were speaking about it I did some research since that and that's I guess not really what I was looking at I was just looking at having um FIA be a central location for grades four to five four to six four to five four to six so not doing a a real true Princeton model where you're taking everybody and mixing them all together I I think we're going to get a variety of options because I think even within the Princeton model there's models right so I think we're GNA get not really I mean Princeton is a very specific type of model from what I understand from my reading okay we're going to get a few different okay I just want to make sure that so you're saying follow up on all four that's going to come

006with the March 10th meeting yes okay good thank you uh next switching into some followup regarding the cooling discussion that we had um pending or as a followup to the governor's and or the state's legislation that was approved in uh December it is our recommendation um to modify some of the projects that were approved as part of capital project 23 um and as you will remember that that Capital project was broken into two separate propositions proposition uh two and proposition three um and I believe I may have these flip-flopped so I apologize um the high school science rooms they were uh included in proposition three so to add cooling into this space uh um the ventilation system was being um replaced but to convert that to include cooling as well and the electric um the

007electrical costs that go with that uh the estimated impact is approximately $280,000 um so we will look to find um cost savings to offset that now that project is out the bid and we expect to open bids around uh mid-February so it is possible that the bids will come in under um if not we can look um to find Budget savings elsewhere one item uh just to consider is um although we haven't awarded contracts yet conversations with different case work vendors um leads to believe we will see a savings of about $100,000 over what is budgeted so um that is the estimated total impact at this point it is our recommendation to go forward and include Cooling in those spaces okay and when you need that from us today or or that is part of

008the proposal that you're approving tonight for the ventilation equipment oh okay um and then the final contracts will obviously come when we open bids tonight we are just purchasing equipment yeah okay so does anybody have any questions on that so that's they're doing the work the ceilings are open governor passed the law y regulation it makes sense to do it absolutely makes sense to do it now versus do it later so anything over 88 degrees the space would have to be vacated um this is second floor science classrooms high school and um this will cool those spaces for years to come so very good um next uh separate proposition is uh Montgomery Elementary School East cenam Elementary School and Berea Elementary School so these projects included unit ventilator Replacements um and while we are not

009proposing to um make these spaces um air conditioned at this time what we are proposing is to prep the units and the work in the classrooms now so that we do not have to go back later so what it would involve is as we are purchasing the ventilation equipment they will contain the cooling coils and then when we award cont contracts um to the mechanical contractor for installation they will include the cooling piping that will go from the univ ventilator and out to most likely a main Corridor where it can be connected later that way when we do come back later to cool the spaces we do not have to repurchase the unit ventilator equipment and we don't have to do the piping and it's already done um so it is our recommendation to move

010forward with this in order to offset those costs we are proposing to take the gymnasium ventil equipment and just put it on hold either defer it to a later phase in the project see where the budgets come or defer it to a future Capital project in which the proper uh cooling um equipment will be designed from the beginning and budgeted and will address it that way right now the the ventilation equipment that's in those spaces will last at least a few more years so we're comfortable with that school G I'm sorry all three Elementary School gy um as part of this project we were not touching the ventilation equipment at Berea Elementary School so it was Montgomery um in Golden yes so if we put those projects on hold for now we will generate an

011expected Savings of 645,000 to offset 475 we are still uh about 170,000 to the good there all right that's all I have for an update on that tonight unless you have any questions questions so when we do go ahead and connect those to um a cooler or Chiller Chiller will that be um designed as part of the gym cooling or will it be a separate CH yeah so I am not an H AC expert but what I'm learning is different situations call for different equipment so there can be rooftop mounted units which we've talked about in the past that will have an effect on our roofs and try to um make that align with roof Replacements um those are for some larger spaces I think like gymnasiums um we installed a very big one at

012the pool last year and then there's also the option for chillers so also in this project we are replacing the chiller at the high school which has provided cooling to that English Wing um since I believe the early 90s when that was um when that was done so yes and so I'm assuming they've looked at the cost of just having individual units in each classroom that are sustaining and don't have to be connected to a central I don't think that was part of this the study for these units um as part of and you saw my memo we are recommending we do a full study to transition cooling districtwide um just high level I think a larger system is more cost effective than individual ones but I I'm just I'm not an hbac expert but

013I only ask that because I know a lot of hotels right to individual units because it is more okay okay all right thank you any other questions all very good thanks BR okay all right so we're going to move on to the consent agenda so I'm going to ask for a motion to approve the consent agenda with the addendum and removing the Moa number five Jan Jane second all in favor opposed okay pass 70 thank you um okay so before we close um I do need a couple of volunteers to um to be the lisons for the grading committee uh need two one with one is more Elementary geared one is more High School geared so any volunteers okay Diana and Angela all right thank you okay so we're going to adjourn the special meeting

014take a brief recess and then we're going to come back and start our um our work session okay so Colin thank you for being with us in streaming um the work session is open to public but we're not streaming so I will take a motion to adjourn at 552 Katie and Fran all in favor oppos okay 7 zero thank you thank you thank you