001okay so this is a meeting of the uh the building sub committee um and with us is Kino construction we have uh Ben Carino if you could uh let the camera see you okay yeah over there Ben Corino is the President we have Todd Harrington I'm gonna call him the project manager and architect and Stephanie I apologize I forgot your title uh preconstruction manager preconstruction manager okay and then thank you and then also uh here is the uh the building subcommittee uh which consists of uh Sophie and Ryan and Luke and uh Dan Dan sorry Dan and of course Kate Lucas and U our illustrious um and Chris no I know and Chris Chris okay um and so uh what we're going to do is run down um the uh um scope of work and
002and cost and what we believe is uh covers uh all of the uh the goals that we were trying to meet and uh what we believe is a pretty aggressive uh price with that I will introduce uh Todd yeah I'm G I'll take it from here okay so first I want to I want to thank the team um it's been a great effort for a month worth of work to get to where we are uh we got a lot of work done and to Paul's Point um we have have something that that looks like we can make happen um to give turn it on Todd turn it on on the side so to give you a little background of where where we are and what the effort has been about uh the preconstruction effort involved
003existing condition review with subcontractors uh discussions with the SMS building committee you all uh Kate and T uh and review of the needs assessment report that was previously done so we took all that information and tried to marry it together into a cohesive package um that cohesive package we developed out of that we developed a 41 item uh 41 item list which we analyzed designed scoped out um and budgeted after reviewing the 41 potential items which we're going to get into detail um we developed uh the design options facilities needs and the priority recommendations and we've come up with a list of what we believe are are priority recommendations that Target the the budget price of approximately $12 million of where we're at the um design and priority selections additional education space building an ADA
004Code Compliance increased student safety infrastructure repair SL energy upgrades and cafeteria expansion basically the the concept was to be as efficient and economical as possible and give the school here everything it needs because the bones of the school are really good I believe um it just needs you know a little bit of work so with that being said the 41 item list with with the priorities the the number one priorities that we've targeted uh number one is the new special service is weighing additional classrooms um for $2 million and we'll get into the design of it and the design process at the end of the budget review item number two cafeteria expansion we have a 1380 square foot cafeteria expansion uh item number three is the admin area reconfiguration ation and the interior reconfiguration throughout
005the school that goes hand inand with the construction so we budgeted for that um moving on to item number four um so we started getting into some of the facilities needs and assessment report um and a lot of the code items that need to be updated and upgraded throughout um item number four is a fire code upgrades what this entails is really sealing up corridors there's several penetration above the quarters that need to be sealed and fire rated walls and then there's two sets of stairs that need um some fire doors in in a wall um at the bottom of the stairs and a MAG hold opens um item number five is a uh to furnish and install sprinklers throughout currently we have partial sprinkler coverage in the school but item number five expands it
006to the entire school as well as the associated um water main uh work uh associated with that item number six was in the uh needs assessment report as well as Ada code stair upgrades what that entails is updating the railings so they're currently code compliant and rubber Treads stairs and risers within the stairs uh number seven is Ada signage throughout basically uh Braille signage at all the class rooms ADA Compliant uh number eight is an ADA Bathroom upgrades there's six bathrooms in the back of the school or around the school that need to be upgraded turning radiuses and so forth um number nine where the sidewalks and the flat work in the front of the building over time the Curbing and everything has kind of deteriorated and um some of them some of the concrete
007has heaved a little bit so it's and it's got a little more slope than it needs to have um moving on uh big critical item in in our study was replacing the boilers so we looked at this uh this replacing the boilers includes an allowance for some tank Replacements roof penetrations um startup and testing and electrical rework in this uh the current boilers are original so they they desperately need to be upgraded um uh Ada site upgrades is uh was budgeted in basically to allow access into the playground uh ADA Compliant access um we looked at if you can scroll down a little bit Steph so we looked at uh three different three different mechanical upgrades for 14a involves replacing the original mechanical equipment within the school 14b was a controls and 14c was uh
008an approach we took to get some air conditioning up in the second floor classrooms which can become hot in the uh early uh early fall School season you want to scroll next page please so 15 was uh replace lighting LED lights with motion controls uh this is basically an energy and lighting Improvement upgrade throughout um 16 was additional classrooms outlets in the classrooms the current outlets in the classrooms are inadequate so we need to add some um 17 is a Transformer this is another energy Improvement upgrade uh 19 is an envelope upgrade work and what this entails is basically repairing the sofits um repainting the fascia around the school to give it a new look and um spray foam insulation at the top of the wall to seal it um from Air penetration and then
009below that is item 20 which is removing replacing the roof with 2 Ines of insulation this is both uh uh infrastructure upgrade as well as an energy enhancement upgrade with two additional inches of uh insulation on the roofs um number 24 is remove and replace the ceilings throughout um this was if we're doing the sprinkler and the lights we felt this this was necessary and it makes it a it'll give the whole school a facelift with new ceilings throughout uh fire alarm system upgrade this this includes uh devices throughout the panel has been upgraded can you zoom out a little bit so this is basically just just notification devices throughout um 35 was a arc fault survey that needs to be completing as well as some uh panel labeling and lastly is the uh we
010carried an allowance for some additional storm water treatment in leechfield work um in reviewing with manual engineering more investigation needs to be done on that front um so we carried $120,000 allowance um with that uh 10 10,184 th000 subtotal uh with 15% contingency uh owners rep and the total is 11,967 745 uh Todd yes could I ask you for the folks at home could you uh explain go into just a little bit of detail about the sprinkler system and what that entailed because it was a surprise to the building subcommittee it was certainly a surprise to me so talk a little bit more about what's going to be required to sprinkle this whole building sure the uh so the sprinkler what what the sprinkler entails is um first of all a uh new generator over
011the sprinkler uh it's not co- compliant currently you need emergency generator to run the pumps uh then moving on to a 6-in firan from from the tanks and then into the school a new fire protection room and then sprinkler coverage throughout the reason why in lie of the existing um it's required if we add on to the school anymore we're currently not code compliant with the height and area requirements throughout okay so just to be clear it requires running a new 6-in main from across the street over to the school correct and all the uh the work necessary to dig it up put a new one in and get it into the school correct you know I I wasn't I I didn't appreciate that when we first talked about it that's a lot of work
012it it certainly is and uh we're not we're assuming that the 15,000 gallon um storage right now is enough capacity that's assuming a light Hazard um we reviewed it with two different sprinkler contractors and they were they were both within a tight range great uh uh thank you for that then one more and that is the uh the LED lighting because you know on the surface someone would come into the school and say and say gee the lights look fine why are we doing that energy Improvement and lighting quality and controls is the other portion of that okay are there rebates that we uh that can still make uh take advantage of so as as we get going with the design and specification process we're certainly going to look at that okay I thought yeah
013I thought I heard that there were there were still some uh some State rebates through 2025 on that I I believe you're right we're we're going to look at that take advantage of those yeah any other questions on the on the budget side of things okay now we'll move to the design so the design process um in in the past month we went through three or four different interations um this this being where we landed with option two um the idea here is to stick with the existing classroom module sizes um stick with the existing language of the school and and really keep it simple and give give add some additional needed space to the school the other component about that is moving some of the admin areas and and intervention spaces and and OT
014PT spaces around within the school and U moveing the classrooms Shi in the classrooms and reorganizing those the other part about the addition is if I can get my laser pointed that's not working but up up above the cafeteria we added at 1390 Square ft um there which will allow um gym class full gym class and fewer three vers or two versus three lunch periods I believe another thing we did with the admin area we did some renovation um and what the plan is to have the checkin area come into the office for some enhanced security um instead of directly into the school so we the plan is to knock the window out turn it into a door and then partition off that space and create an enhanced check-in process for the school as well
015as open it up a little bit um and then this is a previous previous generation with a two-story scheme on the left and so these these Steph's uh going through some scoping drawings just different things that we looked at um in the site as it relates to the site just looked at some different options of Paving and so forth which weren't the highest priority right now so we we focused on really just trying to hit the12 Million number and get um the number one priority needs in the list so that that wraps it up um unless anybody wants to dig into the design um or any has any questions on the design um that's that's kind of where we're at right now I want to make one more comment if I may the numberers really
016the number for the work is really about 10 we've got contingencies in there for things we may have forgotten and for owners are up later on but that's you know the the number is really more like 10 um 10 with with the contingency you want to go back to the total it's 10 10 with a contingency so where we're at right now is it's very very early it's conceptual design in this process there's a lot that's going to be uncovered a lot that we're going to find out and so we're carrying 15% contingency because we will run into things that we weren't anticipating Design's going to change here and there and um a 15% is a a number that should be carried this early in the process as we develop the design we can tighten
017that number up and expand the scope or contract the scope depending on where the design comes and the budget numbers are shaping up but is just to reiterate as far as Corino is concerned and where the school board will will end up going excuse me you're comfortable with the school board moving forward should they approve this uh and head toward uh a bond decision that the 12 million is is is a is a good number for the scope that we have yeah 12 million is a good number with the 15% contingency I I want to compliment Kino here we we went through a lot of different design ideas and there are two things that stand out if you go back to the the design um as you said you kept with the language of the
018school uh and and I see that in two ways one you've added the additions in the form and sizes of similar classroom sizes that gives uh Kate and the and and the administration and the school a lot of flexibility in terms of what to do with those boxes throughout uh and the second thing that Kino really emphasized here was the lack of movement of of um any or very few uh existing uh walls and I think that was critical uh to uh to the cost savings that you guys were able to achieve here and just to put it in perspective we were looking at an initial cost uh back in May of about $45 million so with what you've done with this design and this approach uh again hats off to Corino I think I
019think this establishes a great opportunity to to do something in a highly efficient way thank you we can't help it was it was a team effort I mean all of you guys at the table I thank you guys for your commitment to this as a both as a architect contractor in uh taxpayer so I really appreciate it you talk about profit over go ahead ask him to get over here good Dan Crow here uh the 10 million can you elaborate on the uh Does it include the general requirements in profit in overhead I think it does but I think you need to just hear that yeah um at the beginning of this we were tasked with with the um outset of having an all aart menu and so I carried um the soft cost overhead
020and profit with the exception of the owner's rep in in those line item numbers as as a design develops will break this out into a more traditional um estimate but I essentially at each one of these uh line items as a separate project thank you any any other questions we're good Sophie no no just about the timeline with with the expected timeline if it's passed in March what would be the expected so the the hope is um to get a little bit of work done this summer what we can um but that's that's to be determined uh having the additions designed and and ready to go this summer is is kind of a tall task um but we got we got here in a month so who knows but I I anticipate you know most
021of the work happening spring 26 26 or summer 26 yeah and ending at the end of the summer that's that's the thing about the the school projects the other challenge with school projects is is it makes sense to really get all your ducks in a row before you know you're you're mobilized and have everything procured that way you know you really have a 578 day window it's a lot of work I mean we'll have to develop the schedule but um the goal is to get a lot of it done you know at least shelled in inside uh do we have do we have to keep the existing boilers running for not only this winter but next winter uh the boilers I'd like to get done this summer yeah yeah if assuming the bond vote goes
022through sure so there there'll be things that you'll be getting done before you start you know doing the major part of it absolutely but really ending in getting the kids back in school for that August of 2026 that's that's the plan impressive I mean we like I said we have to develop the schedule but you know that's how how I was was envisioning it at this point right so Chris Chris Merck here so I mean phasing has a lot to do with cost so I would hope that we would get this done in a single mobilization start in the summer continue on with the additions you could do you think you can do the additions during school It's Tricky but but we can certainly look at it I mean Ben what are your thoughts we
023prefer to but most school districts that method so to Todd's Point if we can get this will not happen in December of 2025 we will still be design in the additions um lead times will dictate what we can pull off for the summer of 2025 same thing with 2026 um Bo's march to June is doable for lead times um but to your point we don't want to remobilize each time it does Drive General conditions but we really need to get through design design may be six months it may be eight months it may be five months and I would expect there would be budgeting throughout the design phase as well the numbers we have today are based off of preliminary Design Concepts what we do with our design build method is we're going to design
024a 25% run numbers check 50% so there's stops at each one we will not be designing a building and finding out where are designing a building that's going to be changed to what we're currently looking at excellent very good thank you but you're uh the big cost on the existing facility you had subcontractors come through right you had sprinkler subcontractors look at this you had HVAC subcontractors look at this so those numbers you had verified by uh correct by real guys good yeah we have subcontract major subcontractor numbers we have inhouse estimating what happens is we move through design as we start exploratory so that's why we're carrying a 15% contingency um first of all every single job should have a 10% contingency no matter what uh we're carrying 15% on this design Bill town
025does control that we just don't pull from it whenever we want but yeah we have quite a bit of exploratory work to find um Hazmat surveys it's quite a bit of prep work that goes in before we step on site good thank you for basing the timing around my oldest child's uh coming to SMS she will be entering in Fall of 26 so thank you that was Todd's Focus any other question any other questions well thank thank you all uh it's it's been a eventful month thank you thank you thank you