001alrighty our webinar is live our YouTube stream is live Miss McBerry the meeting is yours thank you Mr Gilmer so I'd like to call the December 16th facilities and operations committee meeting to order and we will start with our Pledge of Allegiance please I pledge allegiance to the flag of the United States of America and to the Republic for stand one nation under God indivisible with liberty and justice for all okay all right first up on the agenda but we've already discussed it um are the meeting minutes for the November 25th meeting but we'll um include them for the next month's meeting Mr Schneider Mr Slaughter correct that's correct we uh we do not have a quorum tonight so we'll include that in January 27th meeting okay thanks Mr Schneider all righty so I will

002turn it over to Mr Schneider and Mr Slaughter for informational item update please thank you m m mry um thank you for attending the facilities and operations meeting this evening um for the informational Updates this evening we we have an update by uh Mr Lynch from cha uh regarding the high school project Pro update Mr Lynch unmuting good good evening everybody it's good to be here um I think someone is driving and there's a presentation teed up I can bring that up Dan if you don't have it all right I'll bring it up here we go all right Jamie is this the one we're looking for I believe it is thank you very much for December there we go you can go to the next slide and uh maybe I'll first congratulate everyone because uh

003phase one is on the street advertised for bidding of uh the North Penn high school project so it's very exciting to finally be out of the gate uh just a couple of updates on um current events with respect to the project um on the Land Development front the team was in front of the township supervisors to provide a quick update and then at the Planning Commission meeting on December 2nd we've gotten the first review letter from the township consultant and those responses will be generated along with some revised drawings and we expect to be back at the March planning meeting again to address uh issues and the civil engineering team has identified that they would anticipate right now final Land Development for the entire project anticipated for July of 2025 on the preliminary zoning review

004there's always uh a lookout for items that would require some uh relief from zoning the two most notable ones so far are the non-conforming uses of the existing Transportation building and also the radio site so far um we're on a track that hopefully we will not require any relief for those two items we're working closely with the zoning officials in order to make sure that that's the case everything else hopefully is a lesser item that may need to go before zoning at some point in the spring the um SNY Hoffman team continues to coordinate with pico for power gas and all things related to utilities and so that coordination is ongoing by the design team and we're also working with North penat Authority on uh both water and also the Sewer Authority for sewer right

005now we're waiting some responses from North pen Water Authority at after our request was made to work on the water lines that are on the school district site we're looking to hopefully convey water lines on the school district site over to North pen School District from the water authority and that would also include new water meter pits that are required for the project so we've got a collaborative process going uh there and some of the early relocation of water lines is in phase one that would hopefully be taking place next summer so that we avoid any shutdowns while we're in school um with kids Mr Lynch um this is uh this is McBerry um can you help me understand a bit more about the conveyance of the water lines and the purchase of the meter

006pits is that basically the structure we have now that we own them and these will be additional ones that we will own so in in summary there's water lines on School District property property owned and operated by the north pen Water Authority and So the plan is for the water lines that are on your property be to be conveyed to the school district and two new water meter pits installed so on your property so that everything Downstream of those meter pits is owned by you and everything Upstream if you will of the meter pits is is by North pen okay thank you the benefit here is that we have an opportunity to possibly repurchase those meter pits if all things come together with the Water Authority so that uh rather than waiting after we award

007bids for phase two we might be able to have them early for that contractor so we're still working through that process um Tom held a meeting with North pen Water Authority everything sounded good um but you know with any public utility we have to see how the timing works out okay next slide thanks Dan uh the npds permit for Montgomery County Conservation District um phase one and phase two were in the process of being submitted we had a pre-submission meeting with the Conservation District on December 2nd which was really eye openening for the entire team because the Conservation District went through just about the entire pre-application and the submitted drawings made comments gave them back to the Civil team to make some adjustments for the formal submission it was um a very good uh process

008nothing eye openening jumped out on the page but as every everybody knows with the npds permit this review is going to take some time our submission should go in um from tnm late in December and we've got uh a six to8 month review um unfortunately there's no process for working through an expedited re review with the County Conservation District we did ask um and then for phase one we have an early submission simply for an ens permit for some of the site work that we're doing that's less than an acre and so that justification was written by tnm um and that's going in for the removal of the underground storage tanks the installation of the relocated propane fueling station and that water line work that I just talked about I see a question I see

009a question forming Kathy go ahead I know I I I don't have a poker face do I excuse me so I understood and I'm I guess I'm incorrect phase one did not require an npdes permit that's correct it requires a soil disturbance I don't want to say permit but we we have to let them know that we're disturbing soil under an acre for that sto for the under the underground storage tanks right for the storage tanks the water line and the propane uh fueling station okay we ALS you know so for instance we also have an acid neutralization tank that we're replacing in Phase One and so tnm has done a great job in wonderfully calculating all the areas disturbance and identifying how it's under an acre okay so all my only comment here is

010that when I read this um bullet when I saw it I thought my question was in my head it phase one does not require so if there is a way to pull phase one out to correctly show what is needed and that we can be clear about phase two is the is the phase that requires the mpds perm because I got very confused when I saw this one okay sorry for that yes no I mean you know it just beg the question but if it is about the soil disturbance and such maybe a separate one for that okay can do thanks so much pen. permit we continue to talk with the Township in hopes of of avoiding a new round of traffic counts the traffic engineer has submitted a formal request with his basis for

011using the existing traffic counts so we're waiting on the township for that review our geotechnical investigation is complete our utility survey and and topographic survey is being completed uh on the site based on comments from the township so utility work and completing some uh uh topographic information and also some shots on the regulated dam is in the works right now and being collected by the district surveyor so that it can go in with our resubmission on the next slide more ongoing activities cost estimate for phase one um has been completed a lot of comments have gone um back and fourth we are in the ballpark of $28 million for construction cost on Phase One Construction again plus soft costs and there's about 1.9 million in the contingency in addition to that 28 million for phase

012one so I distributed that to the entire team today there's some comments there's been a lot of back and forth so we'll keep refining as we go Phase 2 design development documents have been received we're working on uh that cost now we've uh assembled a bid alternate list for the phase one bids the entire team was great at putting that list together bid forms are on the street so um we've got that complete list front end documents are now complete and along with the bid forms and so they're in the package that's on the street I thank everybody who completed efforts um to get edits done there there was a lot of great comment uh there the RFP for pre purchase of electrical equipment is out uh those proposals would be reviewed in January I

013know the vendors had asked for a little bit more time so they've got the holidays I understand in order to put that together that'll still be a fantastic help for the project and we've been working recently on how to handle the radio site and how we do the tower design um we've gotten some input from the solicitor on this uh the existing Towers have to be taken down with the exception of the 1 a radio tower and we've got to put excuse me we've got to put a new tower designed together um to put the new AM radio tower up and so we're going to put a bid package together for the unused Tower demo to be assembled and put on the street as quickly as possible we'd like to take advant of winter weather

014on that site to take down the unused towers and then we're working with the team in order to put the AM radio tower designed together Mr L I have a question there is no uh it's not feasible to utilize the towers that are planned to come down to um be used as the am tow nothing's transferable the the simple answer to that is the that new that that area up there the radio site gets two new athletic fields the existing Towers have guy wires that come down to the ground so they all have to come down the new tower would be freestanding no guy wires and put over to the access road to the school so that it's out of the way of the new athletic fields got it thank you okay next slide um

015so there's the the same timeline for the phase one bid which includes k-pod and atorium limited utility work and I might also say that in the construction of temporary classrooms in various places inside the building so bids are due the next date that's out there is January 30th in the meantime we'll have a pre-bid meeting and I'll do a wonderful presentation for all the contractors to show them how easy the job is and how they should uh give us excellent bids um and we'll have this for the board to consider in February with hopefully a notice to proceed in in March Natatorium to work to commence very late May and k-pod after the kids are out in June you see the other work that's happening there and the dates for completion of k-pod next slide

016is phase two renovation and end user meetings continue with Educators and stakeholders of All Sorts um on the project uh design development drawings have been received and are under review we expect to be out to bid in May with an award in late summer it all depends on the NPD DS permit and of course um us wrapping up uh design and still looking at total project completion anticipated at the end of 2030 there will also be an abatement bid for phase two that works on the same timeline as the phase 2 renovation bids um so we've got floors and windows and other things that require uh abatement we've got a new hazardous materials consultant on board and so we're steaming ahead to be prepared for that bid in the spring Mr Lynch do you have

017the date that the npdes permit was submitted the actual date um I don't have that at my fingertips Kathy but I'm happy to we'll get it and we'll get it funneled through to you all right thank you if we go to the next slide um no real change with our Phase 2 renovation schedule we did sit down with the team however last week and look at the sequence of when we do the auditorium because it is a key phase in the work um certainly because of performances but also because it houses band Coral the Arts Etc and those are loud classrooms that we would love to recreate for them so that we don't have to put them in temporary places throughout the building so we are continuing to work on that and we may go

018from a pod to B pod and then the auditorium or we may go straight to FP pod with the auditorium right after we do the apod addition so I don't want to get into great detail this evening on that but that's what we're trying to examine the best way in order to minimize the disruption of doing the auditorium maximizing our ability to start foundations on the addition to fpod in the earlier parts of the project and of course make sure we have enough classrooms as we do this crazy renovation so that we can keep school and service um next slide is our budget I mentioned where we were 28 million or so on phase one we're working now on what we have for phase two I'll update everyone as soon as we possibly can um

019but everything that we've seen is that we're trying to stay right with that same 260 number this slide remains unchanged from past meetings right now and I believe that's the last slide before thank you slide so I'm happy to try to answer any questions that folks have do you have any questions no I appreciate the update on the order of operations and the how to phase things in um and would be really interested maybe at a future meeting just to help understand how that looks so so understand that you're still very much in the works but appreciate the updates as it goes along thank you thank you thank you Mr Lynch thank you the next item is uh the high school schedule uh Mr Slaughter had mentioned some things earlier about the schedule there haven't

020been any changes to the schedule uh this month and Mr Slaughter had mentioned some of the changes that we expect to have next January uh next month so if there's any questions on the this schedule um myself Mr slauter Mr Lynch or Mr Sher be able to answer them uh Miss MCM merer you're you're muted can you unmute please thank you if I have to thank you um I know that there are a number of um actual questions that are on the Gant chart there and so I know we already talked about that we anticipate or you anticipate being able to provide updates on that so um I will defer to next month Mr Slaughter and Mr Schneider to see where we are with all of that but I I like the detail that's in

021it at this point so thank you you yeah as as we go further along a lot of those questions are being answered as Mr Lynch was speaking to earlier uh you know we recognized that there was an issue with the auditorium so we're looking to move that around uh Mr Case has put together you know not only a a phasing plan for k-pod but also we're working on the rest of the building now so we'll we'll get more definition as we go along but we'll have an update for you next month but but but really that this schedule is dynamic and it does change so it doesn't have to be you know that's the whole point of the schedule so when we see it monthly and if there's a revision date on it and and

022you all speak to what has changed that's all we need we understand it then so I look at it as our road map and communication so thank you and the the final item of informational items is is the 10-year Capital plan uh there has not been any changes since last month uh the over the the last month uh there's been a lot of hard work on The Phase One Design getting that out to bid also we're uh working in the uh facilities and operations office preparing for next year's budget so we should have more information regarding the 10year capital plan uh next month for in February okay thanks Mr Schneider all right um so do we is Kaden on today tonight he is not I think he's in the uh High School concert tonight oh

023okay great good for him so before we um go to okay I guess we'll I'm sorry we'll go to public comment does anyone want to make a comment Mr Gilmer uh we have two folks in the audience uh if you intend to make a public comment go ahead and raise your hand in the interface and then we'll get you in order so we definitely have one hand up so okay I'll read the uh oh just one second operator error here's have it okay here we go um individuals attending this meeting virtually and intending to speak to the committee should be aware that they are being recorded in order to meet the requirements of Pennsylvania Sunshine Law it is necessary to record the names of all citizens who speak to the committee during the meeting to

024assure compliance with the requirement it is essential that those planning to address the committee raise their hand electronically and state their name and and municipality members of the audience are asked to limit their questions and comments to matters being discussed at tonight's meeting or matters that may come before the facilities and operations committee members of the audience are asked to limit their questions and comments to three minutes and this is in reference to board policy 903 alrighty up first is Matt chartran Matt I have enabled your microphone so when you're ready to begin please state your name and municipality for the record and begin your comments please okay can you guys hear me I got you all right great thank you again my name is Matt Chartrand I'm a a resident of T Menon Township

025I know I was on this meeting last month and and also at the board meeting um a few weeks ago appreciate your uh your time this evening I just had a couple things that I wanted to kind of follow up on relative to the baseball um discussions that we've been having one is that we did reach out to a uh a company that that does Landscaping just to try to understand whether or not there was an opportunity get new side down on the infield still um obviously we're very late in the year here but they did say that they can still play Sod at this time of year um and it will lay dormant until you know obviously um and we do think that that's something that that we need to take a hard look

026at as to whether or not that can be done just based on the conditions of the field the fact that it was SED a few years ago uh really has has been lost at this point in time so I know coach Monero said he had IMM I think later this week um to take a look at the field was somebody from the facilities operations Department I do think that that's something that we um relative to trying to get some some saw down there um the other thing I just kind of go back to from month there was a discussion I want to you know nitpick over the budget and and what you guys have a lot it but there was something that was said last month that just kind of jumped out to me and

027it was relative to door hardware and there was a statement that there was a budget for $3.8 million for door hardware and I'm trying to understand is that across the district is that just for the high school and is that something that's being done for safety or just for Aesthetics um it just you know obviously like I said that that number I think was one of the few numbers that was discussed last month and it it's of jumped out as as a significant number I know we're you know trying to to nitpick over dollars here to see what we can get to improve the field and I just want to understand that aspect if I could hi Mr shartan do you have any other comments no that's it okay thanks so I'm going to ask

028Mr Schneider um to respond regarding the door hard hardware and you're right there is work ongoing with Mr Monero and the district so that is moving ahead with the administration so I'm ple we're all happy with that at this point regarding the door hardware I will just say from the board end it truly is a safety security effort that is been needed for some time and Mr Schneider I don't know if you could add anything specific to that um comment absolutely um when we're speaking of the door hardware project for an approximate 3.8 million that project has not been put out the bid yet but it is in uh in the works so basically this would be the um replacement of the door hardware on the assembly areas in every school in the district other

029than the high school the high school will be managed uh during the renovation this Hardware is electronic Hardware so that in the case of a intruder event or an emergency um the mass notification system would automatically lock those doors so it is just not an aesthetic reason it is not just door knobs that you would look at at uh lows in the you know in the residential Hardware door knob section um it's electronic door hardware Panic Hardware interfaced with fire alarm systems um or mass notification system so it it is an extensive um upgrade for all of our assembly areas assembly areas are considered areas such as cafeterias multi-purpose rooms gymnasiums theaters auditoriums libraries any place where and cafeteras any place where uh large groups would assemble uh the difficulty with these areas are the

030doors need to be open for Access for students but to lock those doors in case of a um a situation uh is can be cumbersome you have to cross a gymnasium or cross a um a cafeteria and pull out a key to lock some of these doors in The District because that Hardware was not that function uh when it was first installed no one in the 1950s or even the 1990s envisioned early 90s envisioned um the things that we're trying to uh take care of today so the as I mentioned the Project's not out to bid yet that is an estimate um we'll have to see the the cost is when it the project is Bid thank you thank you Mr Schneider all righty thank you Mr Shan for your comments this evening and I'll

031just give a last call for any public comment before we wrap up tonight and I do not see any hands so that'll conclude public comment for tonight okay thank you Mr Gilmer uh we do not have any items being recommended we had no action items so nothing things being recommended for work session or the next Action meeting um I would like to take a moment to thank the administration Trader group um cha for their efforts work um in being successful in meeting our first major Milestone which was the package one bids going out today um it's much appreciated all the work that was there um I have read the document um very from a board perspect perspective I'm very pleased with the transparency of it the clear road map um that the admin that we

032all want when this uh project really steps off in the construction phase and the requirements so we're comfortable and not just comfortable satisfied with the um Workforce that will be the successful load B so again thanks so much all right anything else from the committee no thanks I think we're good I just I'm sorry for the interruption I just want to share that Kathy and I are at the tech school for their um their annual Christmas holiday dinner and we've had a lovely time and I was just informed that I won um a raffle prize of a stu a product created by a student so I'm the proud owner of a new cutting board and I couldn't be more delighted and I we could we couldn't be more delighted to be here tonight um and

033appreciate all of you for letting us to be able to attend and to be able to join this meeting um I also think um Dr Nicholson is also poised to go make his way down to a concert it looks like you're at your office ready to hit a concert too so we know that this is a very busy um season and wish you all the best into the new year thank you m Mrs Romy so yes thank you all for all your hard work this year and thank you for everything that we will continue to do next year and looking forward to it quite a bit thank you Miss mry oky doie alrighty so any other comments or questions okay okay hearing none the next meeting for facili and Opera facilities and operation which will

034be in a virtual format will be Monday January 27th and there is a hand raised Mr Schneider sorry no I'm fine I'm sorry that was a mistake oh sorry okay no that's fine Al righty so again January 27th um and actually um we need to change the date on this for the next meeting it's January I think it is January 27 2025 um at 7 pm so we'll we'll look for that little edit there and other than that um meeting we're gonna adjourn our meeting so thanks so much everyone thank you everybody thanks Mr Gilmer you got it thank you