Verbatim source text

001right and I also like to add that currently right now we're also evaluating another component of the program that once we look at our utilization we're going to have a met impact look at where we stand there's another program that they offer an additional savings program where based on how we utilize the benefits um to see if we're a perfect fit it'll be a a a cost share in other words basically it's not going to cost us anything but if they save us money we split it down the middle and we get additional savings so it'll help the members save additional monies as well so we're evaluating that as we speak as well so thank you Dr Von and thank you all for your um you know faith in us to go ahead and carry

002this out thank you any more questions it's a non action item do I have a motion to adjourn motion my miss Catherine second M Miss Pam all in favor for e e e Mr tuay here Mr mlash y Miss Roy you have a COR Mr ta all right our committee meetings are broadcasting live to access the stream there is a video icon located in the online meeting agenda and a link is located on our district website Facebook and X all right first item up discuss and approve the iril Parish School Board monthly financial statements including the income statement and the revenue and expense summary by fund through January 25 the reports include a compar comparon of budget to actual for each fund including a percent to goal per budgeted account within the funds have a

003motion moot motion by Mr mlos second by m Roy Mr Stewart good evening Este steem members of the school board and residents of B Parish on the behalf of the finance team I would like to extend my EXT my sincere gratitude to all of you for attending tonight's meeting and for your continued dedication to the betterment of the community and the schools your ongoing support and involvement play a crucial role in our success I'm pleased to report that we are making significant progress in relationship to our our revenues as of now we've collected 89% of the projected revenues for the maintenance fund excluding internal transfers and 66% of the revenues for the general fund this is a positive indicator for our physical health and we are focused on maintaining this momentum as it relates to

004any high priority items or or stress points uh we're collaborating with the parish uh to conduct research to gather uh more accurate estimates as it relates to to our sales and use tax collections um and then from there we will have a revision uh that would give us a a better uh and more accurate up-to-date information uh in relationship to that uh as it relates to the expenditures less incumbrance we're we're at 43% expense uh so that's pretty good for a halfway point um but we can expect uh many uh budget conversations and aggressive spending towards zero uh as it relates to zeroing our budgets funds uh as well as grants that's what I have for that first line item all right any comments questions from the board comments questions from the audience all in

005favor I pass unanimously second item is to receive an update in relation to audit finding within the AUP report all right as it relates to audit finding and corrective actions uh the finance team is actively working on addressing all of the audit findings uh in particular uh I myself and my team um we're looking into the budget process which was initiated in this first quarter of the Greg the gregan calendar year uh we're looking to maintain compliance with the Louisiana budget act uh we're committed to complying with this act ensuring budgets are submitted and revised accurately uh we're using our accounting software alio as well as as well as alio support team uh and internal supports and it to help us begin the budget process and create a template for the budget so that we

006can just hit a button that then projects and creates a rough drive for the budget before we actually begin to do the work of uh preparation for the next fiscal year that will cut out a substantial amount of time uh because as you know every line item within the budget uh within that budget that we submit is manually key and um so that takes months we're also because of this this process and need to push of efficiency we project uh that we will have the budget finished by this fiscal year end which will then put us uh at a a substantially better start knowing what's going on in in July instead of having two or three gry months of you know watching uh spending but not knowing exactly how things should be expensed that's my

007update all right thank you that's not an action item anybody else just to follow up you know a reminder we are now required to do some type of response to the audit report every month so again this will be a standing item on the finance committee and last month Mr Stewart gave you a little update on us trying to streamline things with travel reimbursement uh and you be asked later on to refer that policy as we met and come up with uh a way to streamline some of the way that the travel reimbursement works so we're responding to that audit is timely and best that we can m p I am so excited to hear you say you won't have to manually in there those numbers anymore thank you yes any other comments questions all

008right thank you Mr Stewart thank you Dr V uh can I get a motion to adjourn motion motion by Mr M second B Roy all in favor I e e e tagen here Miss Holmes here thank you have a COR Miss hiden thank you our committee meetings are broadcasting live to access the stream there is a video icon located in the online meeting agenda and a link is located on our district website Facebook and X our first agenda item our monthly work order status report Mr Kagan letting yes ma'am thank you um before I get started I I was going to introduce our new project manager today he called me just a little while ago he got caught up in Convent doing a little job and he was in some severe traffic so he's not

009going to be able to make it to this this month but he will be here for the next month so I'll introduce him then thank you all right work order status report the month of January submitted 38 work orders we closed 117 and at the time of the report we had 51 we are down to 34 as of today and then you can look through the um monthly outstanding lift per list per craft heating and air conditioning hit us pretty good with the Ballers and everything that's going on with the cold and then following that is some Plumbing work and that includes some of the busted pipes and stuff like that that also followed the freeze that we had and then on and on from there other than that everything's going pretty well great oh

010Dr Von yes I I I do want to point out because we we're gathering information pretty much on a daily basis still with Fallout of the the winter storm so I've emailed you a few times and and Evan provided some updates as well but we had some major major pipe breakages at Crescent Elementary at North Iberville and at plaman high school all of these uh are going to be several hundred, of damage our uh risk manager Chris Mitchell is working with the insurance company we do have a deductible according to her it's like a $100,000 per site so we won't have to eat all of that cost and we we are working with our female grants management team uh the governor was trying to get all of the parishes in the state as far as

011their municipalities to report all of their damages he did declare uh a state of emergency at that time I think that state of emergency may still be an effect I didn't see where uh he ended it yet it was supposed to go through I think February 17th but if Louisiana ends up qualifying for FEMA assistance then we have the resources already in place to be able to pursue uh FEMA reimbursement on that event so I I do want you to know as much as they got out there and worked and worked we did have a significant amount of financial you know uh exposure with that event any questions Mr ml Evan did this was the the main waterline bust at MSA that that was prior to the storm wasn't it so the main waterline busted

012the one you're talking about was behind the um Chiller and stuff is that were we adding the new addition to MSA didn't they bust the main waterline right that was on the contractor yes okay did do we is that handle is that fixed oh yeah yeah we fix no concerns with it within the next three days we had it fixed and what we did was re rerouted so we busted up the concrete that was in the driveway so it's no longer coming directly through underneath the new building it's going all the way around it but yes that that was fixed within two or three days how did they do that so the plans that we had nothing showed that line or a gas line that's in that area um so it was one of them

013it showed the actually showed the line outside of the driveway is not it wasn't there it was straight through the center of that building so once they stuck their bucket they hit it and it was and we're lucky that it hit the water line and not the gas line yeah so the gas line is not the same area as that it's outside but it's not where it's supposed to be yeah now we got uh whenever we're doing our final closeout documents that's going to be part of the documents is showing the exact location of these areas and that's why from now on anytime we install underground piping that's PVC we always do Tracer wires so we can find it easy they didn't have any Tracer y on us that's why we didn't catch it nobody

014found it because you couldn't you can't read it yes sir and as a followup Mr Basher there was a water Pike bus at MSA as well that was associated with the freeze that's correct not nearly the the issue that we had at the other schools and they were able to get in there late that night and and get it taken care of so there there were two different ones over there Mr J do we have a timeline on when the stuff uh the construction fixing that plagman high specifically is going to be done so we're going to have to be specific on which one the the damaged water line where they closed off with the plastic uh on that part of the wing they start painting all the sheet rocks is is is done the

015mud is done they're going to start painting Wednesday okay cuz I went by that this morning and they had kids pretty packed into several classrooms just making accommodations and they'll be they should be finished this week if they start painting Wednesday they'll be finished maybe Saturday perfect thank you yes any other comments questions from the board from the audience okay thank you yes ma'am long-term project planning list all right first up we got Crescent Elementary this is the cafeteria Renovations um as you read on here we got some the lights have installed I mean we're we're at we're at that opening point so we're going to start doing punch item lists we're going to start uh equipment is going to start doing the training we set up on the 12th and then we're looking to

016start cooking on 12th 13th so sometime this this week we'll be cooking on it and they going to still be some punch items items on there that we have to do but nothing major that's going to stop us from cooking and also using the getting out of the gym and using the cafeteria lunch area dville elementary to cafeteria we still working on the you know see you got some painting installed hard ceilings it's about 50% install the kitchen equipment uh it's about 90% And The fabrication the new tank at the time of the report was about 50% once it gets fabricated it'll be delivered the pad is already poured and ready to go um they're going to start doing the overhead piping I'm sorry the overhead piping has been completed the um Windows all of

017that's done so right now we're just kind of waiting on some finish finishing touchup inside and then we're going to start doing the tank outside at the same time start um installing equipment make sure everything's good to go it's nice and hooked up and it's working properly um so you're looking you're looking at a couple months still on that one um and it's just going to take a long time for that tank to get installed shipped and installed pumps put in all the pipe into it so you still got a little ways away for that all right Iberville Elementary the Fieldhouse waiting on final completion we're awaiting the new schedule that reflects the new roof as we talked about earlier in the previous months they had to remove the roof because it was not up

018to spec and it was not installed properly so we're waiting on that schedule so I can give youall a better date of when that's going to happen and right now everything else is moving forward but we still cannot complete a lot of things inside until this roof is in place and it's up to spec I I element the installation was completed so that's the last step of the new exchanger we've got all the water pressure that we need finally on this site we've had multiple leaks just over settling and stuff the contractors came out replaced everything and everything is running pretty smooth right now we still got some hiccups and stuff that were still coming that were still coming out and restarting some boilers and stuff which is another issue but as of right now

019we got the adequate amount of water water pressure and it's a good thing that we replace this exchanger because that was the root cause of it the removal of the garden structure at MSA East so right now I'm waiting for a proper time to start the contractor that submitted me an estimate it's bigger than they thought so it's going to take some equipment to be hauled in that area and we cannot have anybody on site to remove this I really don't want to remove it because it's going to be a lot of cost to doing this structure and I just don't think it's necessary to to take that money and use it it's up to y'all if y'all want to do it I can share with y'all a cost and y'all can decide but I

020think we can just make it to something else and and use it for what it purpose is rather than completely cut it and remove it remove all the concrete and all of that y'all just let me know whenever youall ready and I I'll share with you I don't have it with me today but I can share y'all cost as soon as he gets the correct cost but the equipment that has to come in you don't have the cost no ma I do I got a it's a rough cost but I don't want to share it to even because because it's the equipment that they're going to need he said it's bigger than we thought when we first walked this job with them they thought it was a 4 in columns they're 12 and they're thick

021carbon steel entirely so they have to cut this thing with a welding machine they have to cut it up in pieces and out oh they got to get big equipment in here and he even he said man I it's not worth it but if y'all want to do we can we can talk about that later on come up with some pictures with a different design and create something else in that spot that's what I'm thinking I mean we can do something with it but I don't thinking it is the best op I would like it to go somewhere else than have to just f with that yeah I mean we can always do something with it later on we can actually use it for what it's made for one day I mean I don't know

022but I think maybe clean clean it up so it can look neat yes ma'am we can do that seats on it way people can sit but so what exactly did it do ma'am so what exactly did it do what is it it's a garden so you you you put a massive amount of soil on top and you the roof and then you kind of sit underneath it and it has to be built so strong that's the purpose of it I don't know what it's called a flower pot it's like a flower bed but Square Tubing able to just plant flowers flowers or plants on the outside and it's a big deal seem like we we ought to be able to get the kids to come up with something I think so yes ma'am composite or

023some kind of plastic seating or um a decking board some that plastic decking board that no splinters or anything like that we can do that and kind 12 this far is working but they're going to bring in material because it has to acclimate to the weather for a period of time and then they're going to ceiling all your your Crest in the middle is gonna be brand new all of that because we had to do that to yes ma'am start they're gonna start bringing the material this week yes ma'am okay and it's going to take he's told me three weeks to get the job done great pre Edition the um the footings were are complet at the time the report of footings are completed and they started exterior wall and structure so they started you

024know that includes the uh Plumbing that includes electrical all of that stuff so they're going to start all right North cafeteria Renovations punch items list we had about 95% still just tightening things up a little bit kitchen's running really well equipment is running good I think we're good good to go there we just got some little punch items that we're going to take care of this month and it should be off the list by next month new building um on the building G site cleanups ongoing and that's going to stay continuously the CMU block is ongoing as you can see it's about not halfway up but they got up to the first window which is about 8 foot um and then they're starting to do their rough ends and that's just going to T continue

025and if you've been out there lately they've done the structure for the um the elevators and stuff like it's really you can start seeing it going up it's looking very very good plagman high the painting of the stucco and fascia has started we started the soft wash and the job has been rewarded and waiting to start time but that was a start time of painting weather pending right said this week would have been a great week but we got weather coming on Wednesday so we probably push it back to next week to start painting because we just don't want to conflict they started some painting but it's not I mean it's a lot of painting they're going to have to do so we're just we're going to watch the weather all right now the JROTC

026room has been completed it looks very nice and the the instructor um for the jail dream he really likes it Evan I know it's not on here but the cafeteria at plam and high yes ma'am where are we with that yes ma'am so we had a walk down again today um we're starting moving forward on that so we're probably going to come to the board in March with 90% drawings so ask for permission to advertise to then May 27th will be the start date we'll come back on May 14th I think it's May 14th the next board meeting for May to accept the bid and then start date will be around that may 27th and then we're going to work through the summertime to get it completed right we've been working with Miss Alita going

027through what equipment's being replaced and all and it's it's going to be a good little job but it's I don't think it's going to be as crazy as the last two because I was complete stuff but we we've been working pretty good um we will have two trailers Miss is that correct quoting two trailers this time that's a little bigger because of the um mass of kids there and we're going to see a best place to put them we might have to do like we did at Crescent and use the gym the small gym as an area which is the best for us electrical wise because we need electrical water and sewer and they have all of that on that one parking lot so but yes ma'am we have another walk through I think next

028week sometimes to kind of go over a little bit more and um we got some ideas I think y'all going to very much enjoy right it it's not you're not expanding we're just ma'am okay yes ma'am no expansions just redoing some things equipment equipment but you got a lot of stuff in your foyer area and I mean in your dining room area that needs to be done is like the roof the ceilings I mean you saw them at day D I mean ceilings look they're not the proper ceilings for that area for one thing they should be two by twos um so we got that we're looking at floors we're looking at spruing things up security wise on the exterior doors um we got some ideas that I think y'all going to enjoy ma thank

029you and we'll have the 90% drawings uh for the for the March board meeting all right White Castle new gym everything's I'm Sor and along those lines there have been multiple meetings about that particular project over the last couple of months and it's really accelerating now because we want this project to get done uh in the summer this particular one is a little bit more complicated as far as the outside piece you know we've learned from the kitchen projects at Crescent and at North Iberville try to get two trailers or one much bigger one it's not ideal conditions but also that particular dining area is pretty unique in the parish with this wide openness and of course you got a competition gym right there so we've got some security things that they're working on I

030do want to point out that five of you were here when all of this cafeteria uh priority list was put together back in 2022 and this is the next one on that priority list at that time some budgets were projected and I'm I'm just going to let you know now we're going to have to come to you when we do ask you with a higher budget than what was originally estimated now three years ago cost of things are definitely more and there's some parts of this project that were not in that original scope that we think are really going to do some good things for uh for that cafeteria space from a security standpoint and from a utilization standpoint but we are going to work where we bring to you a base and then some

031alternates but uh we will have to request more funding and uh I don't want to get into the political stuff but it is very possible that cost of construction is going to Skyrocket uh if this latest you know action of uh placing a 25% tariff on steel actually goes into effect you know so we're going to be reviewing all of that to to bring to you all the best budgets as possible for all of those projects moving forward but for something we projected and estimated three years ago we already know that it's going to be higher that's correct will we be doing other updates at other schools just Su yes yes we're going to have to anything anything that's anything that's not that's over a year old we're going to have to relook at all

032of them yes ma'am yeah and and also like we did last spring we're going to come because you know the board had come up with this projected long-term planning list you know we we still have that and I think it was last May or so we went a little bit later to you because we had some budget things to figure out at that time and had transitions in the finance department we're going to come sooner to you this year within the next couple of months on the big projects for next year but there's a lot of small things that that maintenance will be including in their budget as well okay because I know eille need some um spruing up a little yes ma'am okay we did we've walked MSA a couple of times yes you

033mean West MSA West and you know we we're trying to identify Fusion is working on some plans the kitchen is plenty big enough for the cooking part that's not an issue seing the seeding you know is the area that we're trying to identify the most practical spaces to use to try to add on you know some additional seating area uh so that work is in progress as far as trying to figure out the best design drainage is a challenge challenge there available Green Space is a challenge there uh and so we we are we've had two meetings for Shing and walkthroughs over there about that so [Music] yeah all right so um let's go to White Castle real quick the new competition gym again we're doing 98% it's you know we're just doing punch item

034list you got a lock or two or faucet maybe not you know up to par but the one you see up top is installation of new catch Basin I don't know if y'all have got many phone calls but I know I have and it's the houses that are adjacent to us where the the fence line goes where the there's our fence and then there's the neighbors fence we're putting a catch Basin right there we're adding it because as all this water came we saw where it was draining and it wasn't draining out and we are now up higher than their property so we're putting a 12 by 12 catch Basin on that fence line that feeds into the main drainage that goes out and this is going to help them with flooding it's going to

035help with a lot of stuff so we did add that into the project and they're were just working on that this week the rain may catch them a little bit but they're going to try to get that done for us pretty shortly so what what about that cooling tower that was leaking yes ma'am coming out we had the cooling tower we have a company that comes and and does all of our major maintenance on the cooling tower nothing was broke it had a clog up in one of the lines and it was back feeding and and shooting out the top of it but the bottom too yes ma'am all that's taken care of but only thing is that water just drains on the cooling tower anyways on the fan on the on the fins okay

036so it's nothing to nothing to worry about no okay thank you yes ma'am central office complex so the CIA upgrades um we're waiting on some um material to arrive and as soon as it arrives they'll start they should be starting here pretty soon uh all right now we go multi campus we got press boxes at East and white and white Council they're about 95% Mr jamy walked them today they still got some punch items list I think it's about nine or 10 on their list that we need to have them do before we you know say hey you're good to go so we're just doing both of them items as punch items and then the restroom concessions on at the same site we are kind of tidying up on one of them right now it's

037that's East I think the last Mr Jeremy was there he um saw that they got a lot done over the last week and then we're going to be finishing both of these projects pretty soon we did find some things that were not like we like but we're addressing them issues as well I have one more question yes ma'am can you give us an update on the football field at North everville yes ma'am the football field we we're moving right along I don't know if you saw the stadiums are down um both stadiums are down and we're just steadily um grading everything start demo we still demo in demo phase so we're still demo demoing before we can start doing any kind of final grades or even prep for that stuff it's still a lot of

038demo and left but we'll get it there's a lot of lot of pipe and a lot of electrical lines underneath that thing so that nobody knew about you know it's one of them kind of things uh as well as the softball field that's coming along pretty good softball field is you know I don't know if y'all seen it in a while but it's coming together really good yes ma'am and also was didn't they have a fire at the baseball field oh yes ma'am we did I heard that through a town meeting but can you help me yes ma'am so the contract on site was welding on the bleachers and then a spark came this was it's one of them weeks that we were off or something spark came lit the grass on fire at the

039home plate completely burned from the home plate back burned up all the new pads the new backboards the new fence the new net all of that talked to them last week and made sure I wanted it all replaced I don't want you piece of nothing together it burned the black uh I don't know what it's called black U poly um uh poly whatever it's called on the fencing so I don't want him to come back with a spray paints replace it all because that stuff is going to rust and since it's burned up it's going to rust now so it's not going to do me any good so I told him replace from point A to point B all new stuff and and that's it so but they're moving forward on it but they they

040lit it up they didn't have any water and the fire things that that that they had apparently didn't work and by the time they got water it had kind of went out of control so that was the fire department they fire department was out there yes no that was not the fire department that didn't have the water this the contract on site the fire watch I guess she didn't have or he didn't have water at the time and I don't think the fire she gave report at our town meeting and that's why yes ma'am thank you yes ma'am I got something EV too I don't know if this is for you or Dr Von but what's going on at Crescent in the dumpster area uh with the yeah um you want me to tell yeah

041I you may not have had a chance to read the email this morning but I sent y'all updates and included that on there so the dumpster pad has to have have hot and cold water and has to have a grease trap according to the health inspector's code those were not installed those were not designed for and uh Mr Thompson is working to get those rectified uh we've been in communication with him and as of Thursday I think he was working on the hot cold water thing first and then trying to get the grease trap piece of it taken care of yes so we have a plan that's that's going to move forward on the hot and cold water we're going to grab it from the prek building that's right there and we're going to bore

042underneath the concrete and do your hot and cold water and then the grease trap um he's working on some paperwork for us the proper paperwork for us and as soon as that comes back we'll start it and U but we just we have to follow our health inspector that came out and looked at the kitchen now she did grant us that we can use the kitchen but she needs to see a a moving forward W plan on the Interceptor or the grease strap and the hot and cold water so she's not going to shut us down right now but she has to see us moving Progressive way to get that done is that an additional cost for the board or No it should not be an additional cost to the board we have multiple emails

043that um that we have with the engineer at the time and it was just a mistake okay thank you yes sir uh and then the greenhouse I wanted to update on the green houses I did get pricing back on the greenhous houses we're still trying to find the best time and and the best way of going about it but the green houses for MSA West and North we may be able to package them and just phase them which is phase one would be MSA West phase two would be North after the building is built because they that area is where they're going to put it you're looking at about say 100 grand for each one so that if we do as a project that that would be a bit out project but you look at

044around $35,000 or so $40,000 for the equipment and then you add another 45,000 for the installation so you're looking around budgeting about 100 Grand per site so yeah I think that's uh one thing that would be very beneficial at our schools yes and this will have you the water lines hooked up it's not going to be a solid concrete base though it's going to be the Limestone base but the concrete would be the footing so we can hang this piece of equipment and it won't blow away in any kind of storm and it's going to have your hbac system or you know humidifying system and all of that stuff just like a a Lutcher high school has it and it's the same design just smaller I was I was going to be 40 by 50

045roughly and theirs was like 100 by 100 so we don't need that big but 40 by 50 would fit perfect in that area at MSA West and then future you can always add to them that's the beauty of them perfect thank you I got a question um you sent me sent us an email about doing a walk through yes ma'am we ever decide on when we were going to do that I can't did we ever decide on when we're gonna do that I was waiting on y'all the email I ask like what's the best time for y'all and then we can just set up a time is the best time that we can do it but I hadn't okay yes ma'am so whenever yeah I answered so it didn't I'll check with him I hadn't

046check I got okay long emails but I'll look at it this week and tomorrow and I'll get back with you at the time okay that's good we have one of our Architects Mr David he got the flu right now so I really like him to be involved absolutely either him or Brad but I'd really like David because he's been a part of it and Mr jerem's G be involved with us and we'll sit down and go through it talk with the contractor and see what's going on yeah okay thank you yes ma'am any other questions or comments from the board from the audience Okay evan anything else on the long term no ma'am I think that's it okay great thank you um the last item discuss and approve granting permission to advertise for the East

047Iberville parking improvements project budget $450,000 yes ma'am this is that Pro that I need a motion I'm sorry I'll make a motion motion by Miss uh George second by Miss Holmes thank you okay yes ma' this is parking lot we have talked about in the past um we finally got the designs going so it's going to be very nice it's going to have the bus lane for the buses it's going to it's going to be very nice so 450 I think is going to be a good good U budget for it and um I think we can move forward on it if y'all agree I got a I have a question so are we going to try to do this the summer so we'll be ready for the football game yes man if y'all approve

048it tonight then I start advertising Thursday okay and then it starts from there y yes ma'am and then next month you'll see Blackman hide as well and we're going to open both of these at the same time so they're a month apart on Advertising but the way it works out we can accept them on the same month and they can start and we'll have them done and they will be constructed simultaneous they could be but they're since they're bit out a difference I mean whatever the contractor has if he has the manpower to do it and if he wins both potentially they could be but they will be accepted by y'all at the same time I know they're they're going to be a month apart advertising but the way it falls out I have to

049wait certain days it just so happen to fall out that they're going to be accepted by the board on at the same time so then they can both start we can give them both the same start date and she depend on the contractor he may win both of them yes ma'am so the one with pla man high that's where the baseball field is yes ma'am I do have a small project going out to demo the baseball field right now just to get it out the way um and I'm actually doing the baseball and softball field just to demo it I'm going to Hydra seed the softball field not the baseball field because I know there's a parking lot coming but if we get that done before the parking lot starts that's going to help us

050in costs as well yeah it's such a ey sore it is that's why I was like look let's just get this thing demoed out the way and then the park it'll be just nice graded ground and they can start over looks better without that little um yeah we got the Press Box down is that is that what you called it I I didn't know what term to use exactly but dear thank you thank you yes it is thank you Evan any other questions or comments from the board from the audience okay all in favor to approve I okay unanimously thank you a motion to adjourn Miss Miss Holmes thank you thank you meeting is adjourned thank you Mr gagna lady e e e good evening and welcome to the oville Parish school board meeting I

051call to order the February 10th 2025 regular school board meeting our meeting is broadcasting live to access the stream there's a video icon located in the online meeting agenda and a link is located on our district website Facebook X formerly Twitter also the meeting can be viewed on Cox channel 21 every Saturday at 7: p.m. following the scheduled Schoolboard meeting the school board agenda can be found on our district website every Wednesday afternoon prior to the monthly board meeting the public participation policy is posted on our district website at and at the front entrance next to the elevators thank you for following our policy roll call please Mr Raj Miss George here Mr abay here miss hi here Miss Holmes here miss laws here Mr mosia here miss Roy here Mr tuer here Miss Williams

052here you have a quarum thank you we will have a reflection by Mr Davin tuer following a moment of silence and the Pledge of Allegiance presented by MSA w m MSA East students kie land fifth grade Roman Tate fifth grade and jayen Lewis 11th grade please stand and remain standing until after the Pledge of Allegiance Heavenly Father we come to you today asking for your guidance wisdom and support as we begin this meeting help us to engage in meaningful discussion and allow us to grow closer as a group fill us with your grace as we make decisions that might affect students staff stakeholders and community members alike we ask these things in Jesus name amen amen pled to the flag United States of America to the Republic for which it stands nation and the god

053thank you Mr tuer and thanks to our MSA e students for participating in tonight's meeting now we will have our Iberville Paris School Board Vision vision statement presented by Miss Pam George with our families as partners the Iberville Parish School System will provide equitable opportun academic excellence and positive School environment so that every student thrives in the path that they choose thank you Miss George we will begin with tonight's recognition presentations if there are any elected officials in the audience please stand first item recognition of Iberville Paris School boards February senior Spotlight Miss Jasmine latche student at MSO MSA East Miss Miller thank you Jasmine latchy is a senior at MSA East she was born to tranisha Simmons and Jason latche on June 27th 2007 in Baton Rouge Louisiana she has two brothers and one

054sister truan James treasure Simmons and Josiah latchie her name Jasmine is Persian and means gift from God her father named her siblings and her with biblical names are names with meaning to Foster that fate as he believed that by naming them this way it will cause good to come to fruition for them growing up she primarily lived with her dad who fostered her views on academics from an early age he encouraged her to be curious and to explore the world around her as much as she could this aspect has followed her throughout the entirety of her schooling and will hopefully continue as long as it possibly can as she looks to the Future she prays to be as successful as she can can be in order to give back to her family and her community

055she plans to study microbiology or biochemistry at an R1 University in Louisiana with R1 meaning a top research school with many multiple opportunities she plans to work as a laboratory scientist as she goes through her studies while she may be unsure as to what her plans are immediately after finishing school as she is sure that she will go far in creating a better future for herself and generations to come until then she will do her absolute best in finishing her last year of high school and applying herself to the fullest when it comes to college applications good luck and ladies and gentlemen Jasmine latchie I just wanted to start off by saying thank you to God for allowing me to be where I am I also want to say thank you to my dad for

056always supporting me and my grandma for loving me uh unconditionally I would also like to say thank you to my school MSA eastburg choing me and my principal and my secretary Miss green who is there in the audience for supportting me in every way they can and I would also like to thank the board and the council for choosing me for student of the year uh for theel district thank you [Applause] [Music] awes next we will have have the consent agenda which is considered routine and will be enacted with one motion discuss and approve a condolence resolution for the family of Mr Douglas bumpers grandfa of Mrs Shantel dun teacher at iov elementary discuss and approve condolence resolution for the family of Mrs Carol Blanchet Pento retired teacher from plaman high school school and sister

057of Mrs josman Bush at MSA West discuss and approve ca's resolution for the family of Mr Johnny Atwood retired warehouse manager at dville Parish school board discuss and approve a condolence resolution for the family of Mr Andrew Drew rander brother of Mrs Faith rander teacher at Dar Elementary discuss and approve the January 13th 2025 regular school board meeting minutes discuss and approve the February 3rd is 2025 executive committee meeting minutes and discuss and approve the February 10th 2025 cons consent agenda as presented do I have a motion I have a motion from Mr abar and I have a second from Mr mlash any comments from the audience any comments from the board Mr Raj M machine please online voting is now open [Music] okay okay online voting is now closed passes unanimously thank you um

058the next we will have the superintendent's report Dr Varon yes good evening on the first slide Miss uh Bailey just to give you a little update on enrollment we've been giving you these numbers each month uh we dropped a little bit from January to February 1st I did use the February 1 count for this one there's two big Benchmark counts that uh the state department collects for us when it comes to funding and grants and uh most of their administrative uh information October 1 and February 1 and as you can see we're up about 19 students from uh the October one count and so as you see these numbers change each month uh and they change on a daily basis the next slide we just want to you know give a shout out to our

059school counselors uh February 3rd through 7th was last week but our board meeting is this week but it was national school counselor week and our school counselors really do a a tremendous job in our school district uh to help our students you know we we removed the test coordinated duties from them a couple of years ago which is allowing for much more time uh for them to actually counsel and work with students uh and Miss bartholomy is here tonight as the uh she's the district contact the the counselor's answer to their princi in terms of day-to-day operations but for all of our specialized Services departments we have District contacts so I'd like to invite Miss bartholomy up to give a few words in regards for our counselors thank you Dr as Dr V stated last

060week was National School counselor's week and the purpose of national school counselor's week is to highlight the work that counselors do in the school system so if you follow our social media last week you probably saw um we posted two counselors or three counselors a day spotlighting the work that they do at their school and sharing with you their why for why they chose the profession to serve as a school counselor um some of the counselors planned a whole entire week of festivities to celebrate National School counselor's week and to get the students engaged one of the schools had a kindness challenge another one of the schools had a um they participated in a your counselor is on your team jersey day um they showcased the CK theme for February they affirmed the school counselor

061with a fist pump um a kind word whatever you know although the counselors were unable to make it here tonight we just really want to acknowledge them for the hard work that they do and the work that they do that really impacts the students and then it also impacts our community as a whole so if you know a school counselor if you see them thank them for the work that they do and we thank you on behalf of all the school counselors for supporting us in our Endeavor with the students thank you and I think we have one in the house she's sitting in the back I couldn't see her Miss Lockett would you please stand she is the counselor [Applause] at she is the counselor at North Iberville Elementary School and we want to

062thank her and all of the counselors for really being champions for our students well-being thank you Miss locket and a lot of these activities the fun week activities were hosted at miss lockett's school so thank you Miss Lockett for all that you do for our kids Miss lock thank you Miss bartholomy and thank you Miss Locka for being here this evening at some point in in the future we do want to come back to you uh and present to you just a a summary and synopsis of what happens in the course of a year and what services our counselors are providing to students on the next slide uh we are next couple of slides actually we're required by law annually to present security updates in the school system uh and we do have Miss Brandy

063Blanchard and Mr James Barker our security coordinator here this evening uh so I would like them to come up and give you uh the current updates going on with security right now good evening everybody how y'all doing um so as far as the camera updates um we are being able to uh get bids and working on quotes getting everything underway um we should be 100% caught up with the quotes by the end of this week and that is for plagman High Stadium White Castle gym along with uh the dorville cafeteria which will be a project that's uh will uh correlate with all of that will be a little bit different because we're going to actually redo all of dorsy ville's cameras because of the uh amount of cameras that are actually installed right now as

064we speak um um the walkth through with the camera companies um have all been going well they are underway and we should be able to have um an update as far as those quotes again like I said as soon as this week okay um and then the uh guest management system we're pting at MSA West which is a way for the public to come in and then they can actually sign in instead of allow and it uh runs through Raptor which is a program that we use for a um the program that we use for um background check the background check excuse me I'm sorry to run the background checks and to um make sure uh registered sex offenders that are all reported onto the uh information and then we are also doing one uh

065at central office which is um it actually is in link with our camera systems which also uses facial facial recognition along with um it it uh monitors the uh checking in and checking out of that person to where as they come in and and they do their responsibilities or whatever they need to do here they can check out and be able to be monitored as to who's coming in our buildings and who is leaving them obviously all right um narcotics detection searches are continued throughout the district um we try to do them as much as possibly as much as possible to work on the schedule with the sheriff's office as well um I know those guys are very busy but um it seems to be doing Justice and to the um the amount of detections

066that we've gotten have been very minimum so I think they are starting to get the message that you know it's a zero policy um um with what we do with the drug dogs um uh contining to do safety walkthroughs can't see um continuing to do the safety walkthroughs um districtwide just to make sure that uh everything is up to date um there are things that we are working with uh as far as fencing trying to get primary and secondary fences to all combine and come together um just to ensure the safety of the campuses um the checkpoints at all schools uh bag searches are something that is done on a daily basis to uh ensure the safety of our students Mr Barker and Miss Blanchard uh these security protocols continue but again as required by

067by Statute we need to give you an update uh we have no visitor check-in system as far as anything uh technological so the pilot that we're doing in here is working out pretty well uh and if the schools are going to get the same type of kiosks that way we can actually have a a digital footprint with the new systems that are going into place where if we ever need to do any type of investigation uh this software basically does a visual profile and immediately it can track all of the movements of an individual so as the technology gets enhanced we're improving that technology in the school system as well uh next slide Miss Bailey is a reminder the academy Lottery and early childhood application period begins on February 21st uh and it will be

068an online application however we will have paper applications available and all residents of Iberville Parish will soon be receiving postcards in the mail as a reminder of the application period and the next or last slide are just some important dates that are coming up in the school system this coming Friday is a professional development day for all employees uh and that concludes my report thank you Dr Von uh next we will have governance busness our first is to discuss and approve the February 10th 2025 Insurance committee meeting recommendations there were two items on the agenda and zero items required actions the second one was discussed and approved the February 10th 2025 finance committee meeting recommendations sorry excuse me they're individually you have to get a motion for each one okay so back to item number

069one even though there was no action items uh do I have a motion I have a motion by Mr mlash and a by Miss Williams any comments from the audience any comments from the board machine please online voting is now open online voting is now closed passes unanimously the second item discussion approved February 10th 2020 five finance committee meeting recommendations there were two items on the agenda one action item one item pass do I have a motion have a motion by Mr Davin tuer and a second by Miss Teresa Roy any comments from the audience any comments from the board Mr R online voting is now open online voting is now closed passes unanimously item number three discuss and approve the February 10th 2025 buildings and grounds committee meeting recommendations there were three items on

070the agenda one action item one item pass do we have a motion have a motion by Miss Katherine Williams and a second by Miss poly Higden are there any comments from the audience any comments from the board Mr Ro machine please online voting is now open on one voting is now closed passes unanimously next we have curriculum and instructions campus operation first item on the agenda is discuss and approve Head Start policy Council agendas minutes reports and handouts do I have a motion I have a motion by Miss Pam George and I have a second by Mr Mario mcglashan uh do I have any comments from the audience any comments from the board Miss Ro machine please oh I'm sorry Miss P I forgot all about your comments okay that's fine thank you thank you

071Miss laws okay our Head Start policy council meeting was held January 30th um thank you attached is our coordinated enrollment our phases and rounds any out ofd District applicants will not be allowed to apply or be accepted until June 17th the Iberville Parish School Board staff outside of the parish are allowed to apply during any phase of the registration the coordinated enrollment is February 21st through the 28th Miss Martin you can move that please thank you keep going please okay um and also attached is the selection criteria form we see this every year uh we've made a slight change this past year with some points and of course our poverty guidelines change yearly so that's something that is changed on our report uh on our uh form every year points are given for most in

072need then we have our annual report to the public our winter Benchmark data which is several several pages and this to me is very crucial very significant what our prek students our Head Start students are doing from the fall from when they entered school until the winter Benchmark this this gives our teachers this gives our staff um to know what skills particular skills our our youngest Learners are strong in and weak in and this is the kind of testing that I believe is is very significant and important for teachers and for a school district and all of our all of our schools showed growth some showed more growth some showed less but all showed growth in every skill from fall to winter and so in a few weeks I'll have the spring Benchmark for you

073to look at also our asq results which is ages stages and questions that's a screening that we track a child's milestones and um there's the parents have a phone app if they choose to use that and I've given you board members the the the pamphlet and the book that is given to every parent in our child care centers in our schools and in our family centers very very important these Milestones are very very important and they assist our parents with tips and information to help their child learn and grow from birth to 5 years of age which is crucial because a child's brain is developed 90% by age five so we can see how how significant our program is to our youngest Learners also we have the safety monitoring for December minor and critical incidents

074and thankfully last month we had no critical in incidence with our little ones our attendance report 98% attendance 95% enrollment we have our prek 3 and four registration and what's happening in family services and our fiscal report and our early childhood specialist report by Miss Bello she is our coach and she does uh she works with um our teachers with intensive coaching and uh does a super job helping our our our prek teachers and we have our specialist our our Le our manager education manager report who also gives much support to our teachers our next meeting is Thursday the 20th thank you Miss hiden we appreciate your monthly report are there any comments from the audience any comments from the board machine Please Mr R online voting is now open online V is now close

075passes unanimously next we will have new business the first item is to discuss and approve itep number 0043 for shint that is for approximately 5050 million and covered the SP site doc expansion and the SP site track expansion projects this is a continuation of the older ipac itap under the PRI rules do I have a motion I have a motion from Mr Mike abar and a second from Miss Pam George Dr Von yes so this time I'd like to call Mr Danny sedat from shint to give you some information in regards to this item so my name is Danny sedotal I'm the vice president of manufacturing at shintech I also have with me Mr Jerry Bradford he is our corporate controller and he does kind of the administrative tasks of these ITP applications um and

076on behalf of shintech and Jerry and I who are lifelong residents of the parish I do want to express our appreciation to you guys for serving on the board serving our school system and being leaders here so I asked uh the the assistant to pull up the map of our facilities so if if you look kind of on the bottom side of the map you'll see shintech sp3 that's our newest facilities up above that and to the left a little bit go left some more with your pointer keep going keep going right there so that's our shintech plaman one and two facilties so those are the first plants that we build at the plaman site um this particular project was done at the s 1 and two site but it supports the expansion that was

077done at the sp3 site so this expansion was needed because our loading facilities where we load the materials we make at sp3 uh needed to be expanded because we didn't build those same facilities at sp3 so sp1 and two site is loading the materials that get produced at sp3 so we expanded our ship dock uh we can now load two ships simultaneously at the1 and2 site before this expansion we can only load one at a time um we also expanded our tank car loading capacity so we added loading stations and rail tracks at the facility to allow us to handle the increased production from the expansion of sp3 so while this particular expansion this $50 million piece didn't add any jobs by itself um the other expansion which was a $1.3 billion expansion could not

078have been done without it um the other expansion the bigger one has added about 130 jobs total so there were jobs associated with all the projects but because these are different tracks of property that shintech purchase at different times the itap applications are separate so anytime we do something at sp1 and two even if it's to support a new project at sp3 there will be different ITP applications so as uh Dr Von mentioned in the beginning this was under Governor Edwards ITP approval guidelines in processes and so this is a 20% exemption uh which can be extended out to 10 years so I'm sorry 80% exemption 20% we start paying right away as soon as it comes into service and that can be extended out for as many as 10 years um so that's basically

079what this project was done it supported the larger project but it's kind of separate on the ITP side we do have more of these that will be coming through in the next couple of months for sure there was also some expansions at White Castle where we get the brine that we need as a raw material for making our products and so there's some brine Wells and a treatment system there and then the larger project will eventually come here as well and all of these are under those prior or the rules that were under Governor edwards's administration because that's when those projects were started okay thank you Miss Mr cator for those uh comments uh do we have any comments from the audience do we have any comments from the board Miss Sage machine please online

080voting is now open online voting is now closed passes unanimously thank you thank you the second item is to discuss and approve the revisions to policies GK and gjc as recommended by the executive committee do I have a motion have a motion by Miss Yolanda Holm and a second by Mr Mike abar Miss Miller yes ma'am uh these are two policies that went to Executive on last week um gam K is a new policy uh regarding the use of pronouns and given names and um policy jgc is an existing policy where CLE cell training was added to the student health services policy as well as um granting permission to um provide screenings and other needed trainings uh for students who may have um some non-complex health procedures to happen so the committee did meet and

081we're just asking to um have these policies accepted thank you Miss Miller are there any comments from the audience any comments from the board Mage machine please online bone is now open online voting is now closed passes [Music] unanimously the next item is to discuss and approve sending policies aea BBB and DJ D to the executive committee to consider revisions do I have a motion have a motion from Miss Teresa Roy and I have a second from Miss ply Higden any comments Dr Varon real briefly tonight just to send these over to the executive committee I've sent you some correspondences around uh all three of these back in June you provided the superintendant with the authority to make calendar adjustments in case instructional minutes need to be made up for emergencies uh I do believe

082that needs to be put into the policy uh BBB deals with School Board member compensation there's some language in there that we have to get cleaned up uh to be consistent with the law and djd I refer to earlier in finance uh we want to give you recommendations to streamline that particular policy when it comes to travel reimbursement uh and clear up some areas that the policy is a little bit vague in so uh thank you Dr V uh are there any comments from the audience any comments from the board Mr machine please online voting is now open online voting is now closed passes unanimously last item do I have a motion to adjourn have a motion from Miss Teresa Roy and I have a second from Mr Davin tuer thank you