001I'm call our meeting to order at 601 or so uh thank you everyone for being here tonight if you would stand for the Pledge of Allegiance and Miss algra will lead us in an invocation I pledge to the flag of the United States of am the stand na indivisible liy and justice for all please join me in prayer father we come to you tonight to ask your blessing on this meeting and on the school administration and all p and putner County indeed in our country please guide us and help us to make good decisions and do what you would have us to do and do what's best through the school board in Jesus name amen amen thank you we do have a quorum present and as far as introductions I think we have our usual

002suspects over there so we'll hear from them shortly I don't see any new faces so welcome gentlemen uh first item of business is approval of the minutes which is in your packet was also available online motion to approve as presented Mr chairman unless there are Corrections by other members second motion Mr McLean second by Miss Asia all in favor anyone oppose all right we will quickly move right into project update did y'all flip a coin of who wants to go first if you're ready Crescent City will be first in case you didn't know which school he belong to James move that mic a little bit see if it's see if it's on we're better at building than this than using these microphones um so uh James Marine you guys know me um Bill Elliott uh

003senior project manager with Ajax um we're building we're fortunate enough to be building the Crescent City PK 36 um and uh I don't really have anything but good things to say it's we as an experience it's been fantastic um as far as um taking you through some of the progress we made another video we hope that you guys don't mind um we're going to let you watch that if if you don't mind we'll start with this [Music] been there understand [Music] better [Music] take Mason going up the walls [Music] so hopefully that gives you a good feel for kind of where you know where we are um and and just two two Qui jokes one um Dr H you do not pay for the videographer it's just a talented APM on on site that does

004the videos for you guys um and number two that was not Dr Hunter on the excavators I do have a quick question yes sir that that machine that has the two things that smooth out the concrete Wayne wants to drive one of I have two requests now for heavy equipment operat kind you ride yeah people us have to pay people to do it but we're thinking we're going to start charging you know yeah like a Disney ride adion that's right so Dr Hunter asked a few questions if you don't mind I'll start off by just answering those since um and Dr Hunter do you have them in front of you I know what they are all right so you asked about contingency so the way we do contingency is we you know obviously track the

005original contingency which started on this project is 2,50 9,77 and as we're moving Dollars around you know using contingency for day-to-day things that you would typically use contingency for we track the the current U balance of it and then as a tool for Mr bowling and ourselves um and his team and course Greg and his team we also track any projections so like if we see something that may you know be need to be funded from contingency we also expect that to project so um with that the current contingency is uh 1.85 so you know we've not spent too much on this type of project as you can see um you know we the projected contingency right now is 2.19 so um that is actually is that increase so it's an increase because the team

006has worked to find various credits that along with Greg's team to find various Credit in Travis Woods and Mr Bing examples brick right so if you want to explain that in brief terms and what that is and what it saves it's just an example of some of the things that we're doing the track pay money sure so the project specifications call for a standard size brick um there's options to get larger bricks to build it and on a building this size sometimes they even look better and so as you can imagine if you have a half a million small bricks to lay and all of a sudden you can turn that into 300,000 larger units it saves a lot of money on labor um and material to be honest is less expensive overall so so

007that's why right now we actually have a little bit more contingency we started out with and obviously concy goes back to the the original number was 2.59 theal the original number was 20597 yeah the current projected this is exact is 792 and what's the 185 the 1857 is the current so spent some yeah so we we we've taken away from contingency to fund things but we're projecting and this pretty good obvious projections B these things that we're talking about we projected you know when you add up all costs and credits it's a net half which is great I mean that's that's fantastic we're we're well into the job right the contingency is used you know as you move through the project to handle contingencies so in our particular case we're in very good shape contingency

008ones but like all savings they occur in the future I mean we could we could up [Laughter] Jimmy just real briefly also I want to make sure we pointed out is CRA also had the other item that was the B savings like can change some window film on on the glass around the building which which ended up saving large really was the one that found that one but if you're saving against element of the TMP why wouldn't that settings be back on that element as opposed to well so you can do it we can do it however we want so think of it like you know it's not going anywhere right it's so it it could you know if if Mr buly so chose he and he said hey looks like you're over contingency why

009don't you give us that money back we'd be glad to it doesn't make sense now necessarily yeah because you may be moving money but but if if we wanted to do that as a team we don't care I have two acronym questions yes sir what is me mechanical electrical Plumbing easy enough and CMU uh concrete Mas so think of uh uh Block M I guess I was supposed to know that CU nobody else has I didn't know good I thought I thought i' catch a few of you so uh what are you seeing both of you what are you seeing in projections for material cost going forward you see it still saying the same going up going down so in general terms terms now I'm going to speak in general but your project is safe

010I I understand I'm just asking so in in general terms they continue to go up so we we keep our fingers on the pulse of that pretty pretty well I know there was a spike in January according to enr magazine um you know we engineering thank you and and you know and just just by the fact that we buy out so many projects and get reports of other teams we do know that there continues to be ation on materials there's also a lot of unknowns you know no matter which side of the political AIS aisle you're on there's obviously a shake up which is you know whatever but that could positively or negatively impact construction materials um you know so on the general Trend it's you know still kind of upward I hope that answ

011all right and second half to that question is do you think your subs who have bit on this job and you got tied in uh did a good job of anticipating that I do and and and not to not to Pat ourselves on the back too much but we we did a pretty cool thing um you know that protects everybody here and you know we were finding that subcontractors were when the market was so volatile and it still is but subcontractors were either Lo to bid or they would bid and inflate their number because they didn't know if metal was going to go up the next day yeah so it makes sense right so they hey we'll just double it and here here's a bit right so then if they were get the end of

012the job and the metal was down you would never see those dollars it was theirs so we in an effort to get more bids have let Subs have a comfort level and also be in control of those potential savings we got with the team and we included an escalation allowance I can't remember the value of it it wasn't a terrible amount basically what we do is we ask the subs we say hey you're competitive B you tell us what do you think might escalate give us your price today but tell us what might escalate and so they do they put that in their bid proposal and then we come up as a team and put that allowance in your GMP so that if that sub say hey I told you it was going to escalate

013if they have very verifiable proof that it did we could potentially compensate them that was reported by probably four Subs you know and it's a very minuscule amount of money when you can compared to the size of this project so we are able to account for that issue if it comes up and I think everybody's done real well I mean we've got a lot of materials um already you know pror submit submitted we haven't had any significant U issues where people are complaining about that type of thing so overall we think we did great okay thank you yes sir ra a good question um remind us again I think you told us this before I both of you told us so the material was estimated in the in each each piece of the GMP yes

014the material was estimated yet the school could pay for the materials so if the materials were really go crazy you still have the GMP yeah that's right do matter so but when you when the when the scooter pays for it that is Ted against the GMP and the GMP had the Assumption the school pay for matur right so like if you if you if if Dr Hunter bid to us and we accept your bid and win their contract and you put $100,000 in there for materials yeah that's and and so we said okay um you know Mr School District here's the PO for $100,000 and then his supplier said sorry Dr Hunter it's actually $200,000 that's Dr Hunter's problem that's not your problem anymore because we called it out does that make sense that was

015that's why we're always pushing for hey let's get GMP let get the B out stops the escalation it uh it blocks in your prices I mean that's the whole reason for it so the SC dist is not accountable for increasing cost of materials because they're in each individual bid are you getting sufficient biders sir are you getting enough people bidding well we've already we we've bought out essentially 100% I think we might still need to buy out final cleaning or something silly like that but um essentially we bought out everything so we're we're across the board contracted so we've locked in it okay great and I I know we'll get into the financial a little bit later but as far as where you are compared to the GMP and where you think you should be

016everything's lining up there have been no increase nor do we anticipate at this time any increases to the GMP for any owner related changes or any kind of crazy stuff like that the only changes to the contract values have been deducted and they've been in the form Ro to direct purchase so everything's moving along smoothly um and I noticed the timeline hasn't changed since last time so that's good that was the second question was I comp out of control everything and I got give bill and his team a lot of credit they're doing a great job day to day you know working with subcontractors there's so many things that they handle before it ever get St you Travis and Mr bowling um you that's what we do we you know we handle all those things

017on DayDay basis and uh and Greg and his team as well so um no we don't we don't see any any cause for concern we would immediately report that to M but we don't see any we're loving how it's going yeah what is the CMU it's concrete M unit so think of like cinder block like the white yeah thank you yes um Dr Hunter you would also ask about General conditions of G Staffing GCS or GCS and just that's the element that is somewhat flexible that is cost of the oh okay people construction manager yeah that they Levy against it's a GMP element actually right so we put those dollars in there so that we can pay our staff we can get por the potties um you know rent trailers rent some of the basic

018things that for running a job site in general um that's kind of what gc's and GRS are um and Dr h had asked about the expenditure so um to to break it down kind of the Staffing was um uh the GMP was just over 2 million um we've spent 519,000 the DAT so we have 1.5 million remaining so about 25% used so we're on track there um and then U similarly um General conditions which is what I would expect is very s similar percentage at 22. % so GMP value is 1.2 um we've used 279 with the total remaining of about 946 so both of those are in line 25.5 for Staffing 22.8 for gc's so total together about 24.5% so that's tracking for the completion of the project any other Dr Hunter questions on

019your list no I mean we you know I think you guys are Weare schedule so I won't go that if there's anything else though we're always here we always got to answer questions um you know again Bill awesome job out there his team um we we just thank everybody for letting us work here I got I got to follow up I don't know this may go to Mr B here so I had a um I had a citizen asked me a question I could not answer about this whole process uh once the school's built what about desks uh and so forth for inside will there be an OP is that you so I should be quiet wait okay I can go ahead and answer I like it when to talk about okay we FFN fixtures

020furniture and equipment so um another acronym yeah add to my list and we are currently in the process of looking at vendors we had uh several vendors submit proposals we have narrowed them down actually the staff has narrowed them down to three vendors they went to a school Alice helped me where was the school yesterday TOA but it was in down springs yeah be uh Thursday they're going to the school in Jacksonville and then there's a third one they're going to see so they're going around looking at that we've got a separate budget outside of the GMP set up for fixture furniture and equipment and we will we will buy everything through that right there but we're in the process of selecting right now so the can I sure yes go ahead so the question

021they asked me was this will there be any fixtures in the current schools that can be transferred into the new schools and I said I don't know yes sir they'll be buying for for the new school down the road if there's an opportunity to move it around yes or they can and however I know a lot of times equipment or Furniture gets tagged to a specific school and you have to be careful moving it to another school I think you'll get audited perhaps and and that becomes a no no but that that depends on the money it's so the question was I'm probably not phrasing the question correctly their question was if the equipment was good enough in the current school it may not be it may be not transferable could it be moved over

022to help save money since we're like smart boards or something that are fairly new I said I don't know I'll ask an example would be if if something was built or bought with title one and put in a certain classroom with a certain school like you have to have all of that down to the exactly where it is um it's not our decision and I think that the easy answer to that question is if it's something that's really good and it's really usable and absolutely we'll use it and save some money where we can um but if it's you know just barely getting by you wouldn't put you know I'm trying to think of a good example but tires on new car I saw perfectly we would do if we could make m one one

023of the things we're asking on certain jobs we're asking the vendors to do is come in and inventory the existing furniture tell us what's good what could we use what could we get five more years out of 10 more years not a project that you're watching but the Crescent City High School the principal there has gone with some of his money now and bought some desk that we're planning on using this com coming summer well I think that's a good story to help when we're telling this whole story that's a good one to tell so people know where one thing that will absolutely be transferred a lot of is like um laptops comp those type things as long as they have life they'll be transferred right over but that's a good example I help the

024district prepare a what I call a project budget it's got the the furniture in it it's also got um the touch panel the touch streams so got a budget for those and there other parts and pieces outside of bricks and more sorry Jackie goe that's okay I was just wondering since both schools Pac a and Crescent City are are prek through6 why are we not using the same vendors for the fixtures and equipment why wouldn't we piggy back we probably are we probably are we're just inter we're just interviewing trying to trying to decide the the truth is these schools are far enough out the the two prek to6 schools are far enough out we don't need their Furniture right now the Crescent City High School has got a phase that's going to open up

025this summer we need Furniture there so we're trying to get one locked in for that and me and Sarah jeene were talking before I came in here do we think we'll use the same one across the district perhaps so but they'll have an opportunity to really try them out on the high school project first phase I'm just thinking negotiation wise negotiation wise continuity everything else right what happens to the old furniture you don't use Sur sell it and then put that money back against this or I don't know that there's a market for old furniture but we can sell it we will we'll use what we can yes sir GRE said you said prepared an estimate including this yes sir for school can we get that sure absolutely yeah and what's the rough scale that

026we're talking about for the for the Furnishing Furnishing everything that's in the project cost outside of brck more you got paying your architect your your your soft cost um it's on $70 million it's about $8 million I think or so but we said a year ago it's about 10% yes but but the the U for just the Furnishings how much are we talking about rough numbers $2 million yeah that's thank you y right and it's a good a good point with Crescent City that you're building right there so things that are usable you just move over where now these two schools being brand new right you don't yeah you want to use new stuff all right um well we didn't really get a plaa a update so you can't go anywhere yet but I can

027you can sit yeah thank you guys as always thank you I guess you can sick make them do it you know you know all of it I know all right well it's great to be here again tonight myself Ken osley uh Todd Duffy uh just give you an update unfortunately I thought we we actually do a monthly update video that's shared with the district you know each month at the first of each month I thought they were going to play it I didn't bring a thumb drive or anything for it this time so I'll just I'll just give you the update uh in layman's terms of you know where we're at on the project but uh basically the project at the current stage is we're about 48% complete uh the roof is completely dried in

028um windows are going in place so the some windows that are the glass and glazing that's lagging behind we're plywooden up to make sure we're waterproofed in we've uh we've got probably uh where we at framing wise we're 70% framed out in on the interior of the building uh above ceiling all the MEPS being your mechanical electrical Plumbing uh everything up above ceiling we're at 80% complete um that's with instulation being uh on all the duck work and the piping and and and that so uh what else we got uh drywall finishing drywalls hung uh to about uh 40% or 40% of it completely finished and we've started painting uh inside the gymnasium the ceiling and everything's completely painted the walls are are painted now uh the exterior part of the gymnasium uh the brick

029is 100% complete on the outside so you can see the finished product of it uh we do have all the the the found Foundation brick completely around the entire exterior uh and it's starting to just you know go up to the stucco height and uh and outside you know the Retention Ponds are in place uh We've started work we're actually starting work Wednesday next week uh on Brandy Lane and we've notified all the neighbors of of the activities that we'll be starting on that with uh getting the road work all done on that back side where the buses will enter this the job site and uh and so that's where we are like the overall big picture construction wise the uh Dr Hunter's questions as far as uh contingency uh we started with a 2.

030$318,000 contingency 238,000 200 yeah 2, 318,000 and uh we're currently at 2,1 188,000 uh of what is still in the budget and being you know out of the ground and over unforeseen utilities and things uh sorry yeah I'm not sure what what happened with that but uh that's that's remaining that's what's remaining about 200 about hundred and a little over 100 and uh 48% and we're 48% complete so like our our exposure at this point is uh very very limited um as far as you know changes everything in the Project's been 100% bought out uh so as far as we are with you know the the budget and increases in prices that we were talking about that's uh not an issue with us those you know equipment's already ordered a lot of it's going to

031be coming in the next you know next couple months um starting to you know get equipment hookups and get get things you know now that we're dried in start getting you know the finishes going and we've got color selections pretty close I think like probably 60% of the color selections all been selected out and there's a few other minor things that are but I think by the end of the next week and a half we should have it all as 100% and releasing all of those materials like stage curtains and you know a lot of the little finishes and things like that um so so everything's going really well out there um you know unfortunately just with you know the uh the little bit of delay going vertical and that kind of pushed us back

032or we would have been open for you this August but unfortunately it looks like we're going to stay on schedule and be finished right at the end of September 1 of October so I got a question I think this is is Jonathan Jonathan on your analysis of bond funds for Pac Capri K through six there's um on the expenditures to date was there a copy and paste or am I reading this wrong because it says Crescent City um expenditures on two different line items you're talking about down below Down Below on expenses related to school Construction Top a bottom city were you um what month are you I am in January 31st first that's what you explained Anis can let's hold that question until Jonathan comes up cuz I he did explain it before but

033let's wait till he gets up there okay to go over the finances um I think I asked this when we toured it can you tell us about the roof material it's not anything I've seen what is the roof of the school made of wa no it's a metal roof it's a metal roof but yeah it's got the insulation up up above and okay and just so that's what I've seen going on you saw that on first yes mhm look like solar solar panels almost no it's just the insulation in metal Ro yeah have the money for that wind power yeah and so uh one of the other questions I think Dr Hunter had is as far as the general conditions you know even where there though the job you know is projected out a little

034bit further we're in great shape with our general conditions uh you know with the project being 48% complete uh we used up to you know we're at 35% on General conditions so we're well beyond the uh and and then just running out what we've been running as far as general conditions we'll actually have a pretty good savings you know even at the end of October so we don't foresee having you know to even with being pushed out a little bit further that we're in Jeopardy of needing any more General conditions because of that delay Thomas if you don't can I ask you a quick question I think we talked about this before since the school will be finished in the middle of a school year decided not going to really use it that is where

035we stand today okay especially at the Paca campus just because there's so many uh moving Parts um Crescent City Campus on the other hand that's a that's a totally different conversation because you're taking one school moving the whole got you very close to proximity so um but routs I mean absolutely nothing changes as far as those two School GOC um so there I mean there's a good possibility and right now we're still scheduled open both schools you after next but there's a good possibility that Elementary School in prestent City could open early I'm not going to say at the semester Point give a definitive date but right like the phasing at at the high school once the building is complete we'll move in it because it's ready to go right and you know so There's

036an opportunity for us to do it we may just do okay does that mean you beat the April 20 date for the turnover April 20 that's a final that's a final completion I think we had the your occupancy February yeah I didn't give a finite date I'm always pushing for them to you know move a little bit faster and but you know and I'm I'm I'm but I'm not given a data if there's an opportunity for us to move but once this compl now we can't move all weekend we a little take a any other I don't know if you have any other questions for us other just a comment the third question was are there any subcontracts out of control just to comment on that if if that is the case we really don't

037need to hear about it it's within the GMP but if they make a case it should be contingency we do need to hear right correct now we're everything's completely bought out and we're in great shape with our subcontractors and and uh you know this has actually kind of been a little bit of an anomaly with us um I'm not sure how Ajax has done with some of it but sometimes you always have a contractor really doesn't start and finish the job with you and we have to supplement Manpower and forces and you know knock on wood this has been one of those that we haven't so it's been great to build here and what's amazing you know I live across the street from Paca a and I mean there's people out there all weekend doing

038something yeah even cows I heard oh there are cows yeah and our neighborhood sandhill cranes come through [Laughter] start the kitchen early one the one discussion we had was what about the new tariffs are are any of the materials subject to those tariffs and I think the answer is no I think we're not getting anything from overseas or any place Canada or anywhere that's so that I believe that's yeah it can't get in here so we have to buy it at americ yeah right now I think all of us in our industry are watching that very closely um because it depending on what tariff from where on what items it could affect and it could provide inflationary pressures within the construction industry but it's we to wait and see right now fertilizer your projects right

039now both are are pretty safe compared to where we are bought out under contract hopefully there aren't any any hiccups related to that yeah thank you yeah thank you now we will jump to Mr odm I know that you have not been feeling well but I thank you for being here so we'll take it easy on you I will say I will I will say today I felt like I've I've made a better turn so I was planning on coming to work tomorrow if that says anything um but no I've weekend and last two days have been rough for me um but we're here I Live 5 minutes away so so it wasn't hard to swing by real quick um if you don't mind let's start uh with Miss Jackie's question I think it was

040the it's probably the first clarify yeah are you talking about the bottom part that says Crescent City pre six expenses 11 million that one and then also Crescent City encumbered okay 6 million so as far as the pla update the plaa prek to 6 everything above those two lines is your update the bottom where you're looking at and down is the total dollar amount for all of the bond money so the first area where you're seeing Crescent City prek 6 expenses on the plaa page and the other expenses that's just showing you that the other two pages have 11.8 million in expenses along with the 28.5 million in expenses on plaa pre k to 6 you just bring the two schools together in one p the bottom section of the encumbered is basically um 11.4

041million that is showing up in Skyward we just haven't paid it yet it's showing up where in our system our Erp for another acronym for you so instead of keeping them separate like so we're getting a sheet for Paca prek through six but we're getting it's labeled Crescent City prek through six expenses of 11 11 million um right then you add the two together right here is your here and up is your plaque of pre 6 update this is just showing you so on one page you see everything so from here down is everything from here up is your show um two pages from that where the bottom line numbers match I think it'll be a little more clear two P I had that you see this is and actually if you go back one

042page y that one matches too so all three basically every month you get three pages one for your pla school one for your Crescent City school and one for your other which I explained other originally um is everything before the school builds so the bond issuance Bob gang um which I can speak on that in a second too um so all of that is included on the other page um it's actually been pretty dormant ever since I actually started building School um but it it the bottom half of each of these pages and it makes it easier I can throw a line across there or something and um everything on the bottom half of each of the page just a Reconciliation of all three pages for that and and this right now the the 60

043milon 1994 is what we have left 6 194 is what is left from paid and income right of of the original of both schools yes yes loc 71.6 million that you see just a little bit that is actual total on SP in cat that we you still have control of um in our last meeting and I I think I know this answer we know we got a credit from the tax collector a refund of sorts and then I know we're paying the commission up front the refund does not come back or I don't see it coming back here is it supposed to or is it supposed to go towards the bond repayment account which is probably where where it is I'm assuming going back to the Deb service and to me that makes sense because

044that's we want to pay the debt off as fast as possible so the actually let me see it's on if you look we're already showing for25 on the second page the other page yep um it shows for 2425 we've already basically contrib 160,000 commissions that is where they're and um that includes uh advances we gave them because in the same statute uh it required that we advance 11 12th of their commiss prior year and and it makes sense because most everyone's paid their property taxes by December so we're going to share in the spoils when it's all over yes good and bad um so I I kind of mentioned Bob gang there for a second so I'll also well I guess I know on the thing on the agenda we have a bond issuance so

045I can wait on that if you'd like um if anyone has questions on this are there any other questions on actual expense reports yes one uh on U you we have this situation out where we have to itemize all the materials because the school board bu these are dispersements made by the school board we Tred that maneuver to try to get around thebody said can't do it um but in the not count of the others but on the actual statements for school are all those payments within the scope of the GMP and there's any of those contractors not in the plan we made payments to you we got pick one got interior exterior Enterprises were they in the plan to start with for uh black grk you talk Owner Direct purchase yeah yeah that would

046be one of the vendors that's cont it would be so my question was are there any that were not in the plan no that wer under contract right okay everybody's under contract for which we made it to whom we made a payment correct yeah and I I will I will say most of the names that I see coming through now when I update these for you are names we've already had on one these months some are obvious I guess are am all right do you have a question no no okay good ja oh she needs your jacket that's important any other questions on individual expenses um I don't I printed off the timeline for the next Bond issuance I don't know if it's in our packet but I found it online somewhere anyway if you

047want to if you want to go into that or start wherever you'd like well I will say because of my last few days I actually don't have it printed out in front of me um real quick before we move into that the last page I included an additional page that short like that that is just showing you the accumulated interest that we've gotten off of everything what's the bottom line I don't have bottom line is currently just over 8 million right that's the entire comp from start to finish that's added to the cor so the interest will go back into basically total end it sitting there we can pay back right was that more or less than what you expected or did you have expectations I don't think we I did so I didn't start

048with the first issuance so I wasn't in those numbers discussions but I would probably say that yeah I don't think that we actually ever talked about it until it started we told we 5% and we're paying about 4% Yeah we actually making money as long as the state doesn't stop I know when I was we were getting more than 400,000 a month I was it was more than I was expecting but also we all know that don't um I don't have the timeline uh he he did say he printed it out so we can get you get a copy around the table if I want to um but the goal is I think the first official email was sent two weeks ago maybe um all of the executive was was on it and um it's

049planned to be done by the end of the fiscal year going out for the same exact amount doing 99.5 again send just up under the 100,000 100 million threshold um um uh right now the plans are to leave like as far as Investments and everything leave that the same stay with the same company Bob gang um apparently in their their original letter it did say their first round was all of their expenses plus 80,000 profit that's what they were making off of it and their expenses on on these sheets was what was that it's a 50% gain all of all of um the expenses on here total 191,000 for them going into that I want to say 25,000 of that was a onetime bond validation they don't have to do that again that that 25,000

050won't come back I believe it was 58,000 was tax collector related so that shouldn't come back so the 191,000 you're still going to be looking at um a little bit over 100 Grand just over it but it should be substantially cheaper than everything we spent with him this time um his base profit over expenses dropped 10 grand and that was in the original letter that came around the first time and you mentioned an email to me the cost of getting our ratings is going to be higher could be that is uh according according to Laura how from pfm that is the one true variable whatever they charge for the radi and that's fit and can't remember hear the other moody maybe so for us to issue our bonds if we have a rating on it

051it's much more marketable than if we don't so and their their fees last time which would be on the analysis Bond other page was 62,000 for one and 615 for another we know what they do we don't know what he just builds which is not uncommon I will say to determine the tax collector fees and everything I pulled up all his little invoices I went through them they list out he had a three hour phone call with so and so he sat down and met with someone for so long I mean he that um so that's about as details as we can get as far as what he does but uh I know the other day when I got on the phone call with him when we discussed U his fee uh he talked slow

052but I was P to tell you how much he was going to charge that's six every six minutes minutes seconds the question is he's got to explain what he does right if he's just sitting there in the loop because of the financial circles and getting a big fee that's not uncommon for that business it's it's something when talking to them it was expressed not by him but by the other uh group we work with pfm that you know one we're paying for one of the best that does Bond Construction in state um but it won't make much of a difference starting off with someone new you're still going to have a lot of um and they're going to have to do work he's already done with some of the stuff so um he's good at

053what he does and he's always been good and easy for us to work with so um I have no issue with it it will be substantially 885,000 cheaper um so so a quick question on the timeline and I don't know um I I attached some to your email oh you have your copy yeah I printed it out I attached to the email I sent you all I on the time April 15th is slated for the school board to see all the documents and approve it does that mean that those expenses should be in there in that or do we know for sure um if we gave them expenses like I'm doing here they would have expenses all the way through March um no I mean for the actual Bond issurance I'm sorry oh okay upcoming

054yeah I would I would I think that's the time the board's supposed to plan or approve it all so yes I would assume it's it's a contract at that point so I would Mark that on our Calenders as if you don't come to the meeting you can pull up the documents on board docs and at least review what it's going to cost what they're anticipating so at least we have an idea well will the school board think about it beforehand before they I don't see any in the room I I hope so I would hope so um are you saying the rating will be similar to the first bonds that were issued as far as what rating we get yes uh that depends on what our finances look like compared to last time so I

055will say um there's only been one instance where I was concerned that might affect our rating it is Home Depot who is pay to work with their credit card Ser they shut down our credit card with them because they had something that was 160 days past you I looked at the file they gave us and it was about 15 items all but three of those items were actually paid they just applied them wrong and didn't hav't corrected yet talking to Laura how with pfm it was such a minor thing a minor amount and everything that she doesn't believe it will affect us at all but that's the only thing that's come up to me that's like this could be an issue but lur how doesn't believe it's enough of a dollar amount or Mark or

056anything to affect us so um I would trust their opinion on that do they look out there when they're doing a rating do they look at tax deeds how how many tax deeds are out there what's the value of uncollected Revenue in our property taxes are they looking at that it's a pretty small number because they said value count7 billion this is my first time going through ratings um I I they know it's guaranteed because I'm backu property tax right um so I would I would love to say yes but I truly can't say that myself yes sir on the on the amount I think CH just said going to go for another 100 million plus we're going to spend 150 to 160 on the first two schools correct that leaves us roughly 40 to

05750 to spend on the third school that means we have to go out the bonds again in the middle thirdd school that's not the fourth right is that good strategy it's we I actually listened to our meeting um earlier and from last time and that's really the only thing we can do we don't we can't hold the funds for too long we get in trouble true but we also can't wait and Jonathan you mention School District can't float can't float $30 million until we get bonds issued so I think we're making the right decision on timeline because the new the next phase will start probably before these schools open it's already started okay already started so um I think we're doing what we're supposed to do as far as the timing as opposed to borrow

058more right because you think we'd have to Flo but we're going to make be paying off the first two schools paying off what the cost yes50 you have to spend all the money in like it's either three or four years the concern is if we grab 200 million you won't have that spend off at that time and then we'll have to pay back or have penalties yeah there's a very strict time line to spend it me like's so what what'll likely happen is a year down the road after this bondu we'll have another and the reason we do 99 million 500,000 it's supposed to be just a little yeah it's there's break points cost more to do 100 so um so so the the timeline you just got a copy of so that meeting April

05915th would be the one to pay attention to or the week before that to see if all that is in the board uh for the board approval if you want to look at those things and then the rest of it is not anything we necessarily need to worry about I'll get to it in a little bit about our our next meeting um we can decide when it's going to be but I think follow following the second Bond Bond issuance might be a good time to do our presentation to the school board or kind of our update that we're supposed to do um we can talk about that in a minute so Jonathan P May yes sir Jonathan procedurally then and and I probably should know this but I don't did you send this information that

060you're going to have for the April 15th board meeting out ahead of time or do you spring it on them then uh always the week before is what we a for so the April 8 oh I see it okay I got you I got you sorry I should have seen so technically to be on the agenda it has to be a week early or it has to be an emergency item yeah anything even if it's after midnight that night it becomes an emergency item so it's a whole different section that you have to individually talk about okay but you can send anticipated costs when you send your package to them instead of having Wonder whe they're ask well it'll I mean it'll it'll have to be in the board agenda documents I think so yeah

061whether hopefully everyone will look at it if we get the money on June 19 that's roughly what when it comes we will not have spent $100 million on the other schs right that's so we should be no no are you asking them to no no no at our I'm just trying to make sure the timing is right I I don't think we'll be $100 million in hot by June neither school but you've been adding the two schools together well if the if October I would probably say you're right we're spending about 6 7 million a month right now sorry just less half a year out you're probably right but we also can't wait till all the money to go out for money because then we're holding up everything especially if the next phase is already

062started you will have to work any other look like it looks okay we got $67 million dollar we're spending maybe six a month that give us consider 8 to 10 months we should be all right I will say when I first talked to them the plan was um we gave a date or 25 million left when we wanted to get everything going and um by the calculations that you kind of just threw up in the air 7 million for 4 months 28 million off you're going to be looking at 40 million we have left so it's not far off that sounds right so with this next round of $99 million for the bond and you've got a closing date of June 19th then that's going to hit the property appraisers and the tax collector's office

063just in time for the August tax proposal taxes to go out is that right and so that means that whatever somebody is paying right now on a lined item for their bond for their for for The Debt Service on their property tax bill that now for the end of 2025 is going to be doubled it is dou the same increase that it hit this past time um and as far as the first com one of the first comments you made is they better know about it this time is what they better know about it this time because that's that was one of the issues last time is they didn't know about it till too late and that's where all the issues came up because they didn't uh plan for it so we didn't plan for

064it like they didn't reach out to us till after we had already done our budget so now we will know so not only they need to know but we need to know as well so we can put in our budget as well because that's kind of why we fought it way we did it because we didn't have thatone all they came after our budget was already submitted and can't be changed they came and said hey you got to do this so you're at the school district's new budget that goes for a vote this summer will have this new $99 million in on that budget to be voted in and then so the proposed taxes that people get in their mailbox in August that's what I'm saying are going to be doubled for The Debt Service

065am not not the of the tax colle right not the tax collector I'm talking I'm talking about what every tax P every person paying property taxes in the county what they're going to see in August now if they do a comparison their August proposed taxes in 2024 and now they get a August proposed taxes in 2025 their debt service line item is going to be doubled um should be uh if as long as they don't I mean as long as they're ahead of this one because last time from my understanding everything they weren't ahead of it and that's why they reach out to us late and we had to handle it after the fact um so yes um and I mean I can byy all means reach out to them and make sure they're aware

066of it um but they're they're aware that we're having to go out for more Bond money they don't necessarily have the dates yet I'm I'm just concerned about the Public's perception of we don't even have these first two schools completed and now you're and now you're asking the the taxpayers one and I I know where you're going with that one but one thing to keep in mind is if we let's say we delay this issuance till August it gets issued in August doesn't make it on the tax bills there's an interest payment due six months later on every bond that was issued and if there's not money coming in to pay for that it's got to come from these funds so we're essentially going to be paying interest out of our out of the bond

067funds we just raised to essentially float that because it's not on the tax bill yet that'd be worse because we owe it to the taxpayers to tell them what the cost are going to be soon as we know right we know it's going to be another 7 Mills or whatever that's going to happen right and they should see it this year cycle now if it's if it's delayed and it's not anything we can control we're going to have to deal with it but we got schools on construction that we have to pay right that we're committed for committ we're committed over 100 so so we just have to make sure that the school board does really good explanation in the community or have some type of that's why they're the school board and we are

068an advisory oversight committee yes but also the State of Florida they're even looking at cutting property taxes out oh don't even get this that that that we'll be here all night if we start talking about that no but I'm just you know when we're talking about because we well if they do that all the small towns will try up and blow away well I but it's conversation because I'm hearing on the news almost daily now so it's not something somebody said and they dropped it it's going on a regular basis and I see they're they listening too because I see their heads bothered I know there's nothing we can do about it at the moment Dr Hunter can't we be proactive and and ask the school board to be sure and submit the fact that

069we are going to have another Bond issuance talk about for taxes will include some kind of noce public yes sir because right but we can't let this slip by because people don't communicate yeah and then all tax bills you me to email uh Phil ly on that and just ask him to be proactive on it or yes you could as the this committee okay appropriate we'll make sure it happens in now when would I'm sorry just I I get mixed up on the taxes so the things will come out in August saying what your taxes are going to be and they actually occur the following January is that right uh tax bills go out what they're doe in April April ail the last month you discount start in November end of October and the notice

070goes out in August right right so we got give you three different scenarios if you miss August and hit October that's bad that's right right so I think Jared what you're saying s over an email from us as a committee that if everyone thinks that's proper that we are suggesting some Community awareness of what's to come right I mean I had a phone call with a friend today and she asked me that exact question she me it's got a double CU myb yep just today yes eventually yes it's going to Triple she doesn't like that part either Noe I haven't heard anything positive so far on coming up with another bond issue with this well nobody likes taxes that's I've never met anybody that wanted to pay more I mean I'm just saying it's got

071to be marketed heavily because it's not did you have a question no oh okay no I I was just thinking it's too bad that only 21% of the putam county voters turned out to vote on the bond issue when the other 79 didn't and now they're getting bit in the butt they're going to be mad but they didn't turn out and vote they need to learn their lesson Civics Civics in schools cic just so you know yesterday the Senate s sp52 filed a bill to start the process of a study on elimination of property taxes in the State of Florida um and one of the things they're going to study is one of the Alternatives uh for basically the things you mentioned like school districts and others but they are moving ahe sign off on

072it and they moving but understand this even if they get rid of taxes that has nothing to do with the special fees like the city puts on for the fire fee or the county puts on for the garbage fee or the bond issues that the city and the school board's got those are not taxes they're special fees they won't be affected by it so still get you'll still get a bill of some kind just they got to have something to do let them study it well the bottom the bad news is if everybody don't get rid of taxes if they get rid of taxes taxes are C cut cap to 10 10 mil if they get rid of ta taxes they they put fees on you and fees have no caps they go as high

073as they want and they can really get you bad so don't just jump and say I want my property taxes gone because if they're going you're going to be in real trouble with no caps and no help yep the alternative is going to be state income tax and that's going to go for real no they'll do worse than that 15% sales tax yeah probably that's what they want to get everybody to visits special fees um on anything else for Jonathan he looks comfortable but he'd probably like to sit he like to go home a Mr bowling this may be for you I probably should have brought it up it's on the agenda but on I know the school board had a discussion recently on the traffic impact now that decided that PL a and Kelly

074Smith yes um is there an update on doing the traffic study or do a traffic study two years ago um and essentially they didn't change anything they they would not move um first of all it wouldn't extend it further um the speed zone or or even move it to the next corner where the U parent pickup traffic was they just suggested that we reroute the traffic a different way um so that's kind of what it is right now we are internally looking at other ways when I say we people like Greg and and ERS are studying ways to um engineer that site as you know we've already acquired an additional 52 acres to make it larger um to pull as much traffic off of the uh Highway as we possibly can and stack it onto

075the traffic um the RFP for that school was put out what a week ago yeah the days are they put up um both next two schools next Bond ISU were both listed 14 so they run through the seven and those are for Architects um so someone can get in and start doing you know very detailed designs uh right now it's all been just site plans you know I'd like to say something that's possible but I don't know it's possible until I let an architect look at it and and then give me just some different scenarios different building placements and traffic patterns to tell me yes this is possible um now we're getting down to needy gritty of act actually hiring an architect for the next round the next round being um the two schools that

076we're we're looking at on we're talking about down what about on with the Horseman Club school um I know we tal there was some talk about extending or putting in a Dell Lane on 19 or some other do we know where that stands want to talk about what's going on yeah we're we're meeting we got I saw CL were talking well both both of them just saw club that there's with the engineers and and the county they're doing they've been doing some study on it coming up a possible design so one of my from the bond standpoint is that so let's say you put in sidewalks or new Lanes on is that incorporated in the cost already is that not so is that a that's a change order that could cost us money could be

077direct cost in school board you it could more than likely probably cover that a contingency okay we've done some rough estimate budgeting numbers there's sufficient funds Andy okay okay okay will Thomas can asking a couple questions surey th talking about down the road um the reconfiguration new down in Melrose is that dollars that we could go back to the state for and ask like we did Crescent City um so it has to be special facilities one yes we uh we're looking at Crescent City Junior Senior High being the next special facilities project just because high schools cost so much to build and what we have to pay back won't change it's uh essentially three Mills what we have to pay for as our contribution the new school so if we build a $30 million school

078we paid 25 million back we build $150 million school we pay 25 million back so obviously special facilties dollars to pay back the big you can only do one of those at the time and you can't start over the next one until you finish paying for the first one so there Crescent City is going on right now the Junior Senior High School um a lock in junior high school you misspoke CU like you said City would be next and Jonathan and I are both going what yeah didn't City now inter and then P would be third yes okay thank all right quick note on that since it just came up in conversation they're actively talking about um two weeks ago I met with legisl legislators in my cohort Finance they're actively talking about getting rid

079of that uh payback having something with it where it's not there or it's extremely reduced or something so very possibility we be looking at our next special facilities being that would be nice any other questions for anyone in the room any other Committee Member comments or items you wanted to discuss that we didn't talk about key lime cookies are really good by the way I'll mention that I was able to stop by the s i just there's really two things that are happening one is what is the progress that you can get a number my sense is the real number better than just looking yeah a true story quite nice um our next meeting is up to us I I like staying with the third Wednesday of the month we just need to pick a

080month um the I don't and it's I mean it's totally up to y'all that the next big item is the bond being issued that's not going to happen till mid June we could we could wait that long and have a meeting in July although July is not necessarily the best month for vacations and things like that it was tough last summer when we tried to do that we could have one as soon as May or possibly the mid June I know I can't make M but that shouldn't have um we're required to have I think four meetings a year if I remember correctly June the bond next Bond issues coming out in June let's do it mid June okay but what's the date it'll be June 8 uh well June 18th would be the meeting

081the bond issue supposed to be finalized June 19th but with I mean that could be a few days before or after depending on who could either meet the week before or the week after well I like keeping it the third Wednesday to be cons which will be June 18 June 18th yeah that's that's the third week but you want to meet on on the 18 M third Wednesday oh okay everybody okay with that yep would you like me to see if pfm can join let's the the people that do the B how much that going cost asking no it shouldn't cost let's you and I talk to Laura maybe or you can ask Laura if it see how things are going up to that point and she can just maybe come in on zoom and

082give us an update because ask inter come so we can ask because the biggest thing with her would be kind of what expected rate we're looking at and how the Market's doing everything be I think I heard say but June 18 cling closing nothing should change all right so June 18th will be our next meeting I don't see any members of the public in here um there's nothing else I'll entertain a motion to adjourn everyone in agreement stand up and leave